Project : Wayside Amenities For Sikka, Jamnagar, Gujarat Client : Tourism Corporation of Gujarat Limited (TCGL), Gandhinagar Architect : ARG Creation Pvt. Ltd., Ahmedabad FOR CIVIL WORK SPECIFICATION OCTOBER 2013 Page 1 of 88 SPECIFICATION – 2, 3, 4, 5, 6, 7, and 8 (Item No : 6, 7, 8, 12, 13, 14 and 15) Providing and laying CEMENT CONCRETE 1:1.5:3 ( 1 Cement :1.5 coarse sand : 3 hand brocken stone aggregates 20mm nominal size ) & including cost of necessary,form work, compacting with vibrator curing centering & shuttering in true line and level etc,but exculing the cost of reinforcement for RCC work in (A) Foundations footings, base of columns and column upto plinth lvl.… etc., (B) Ground Beams / Plinth Beams / Tie Beams (C) Wall Cap / Coping (D) Ground Floor Column (E) Ground Floor Lintel & Sill (F) Ground Floor Slab (G) Ground Floor Slab Beam for any tye of cross section area complete as directed by E. I. C. 1.0. Materials: 1.1. Water shall conform to M-1. Cement shall conform to M-3. Sand shall conform to M-6. Grit shall conform to M-8. Coarse aggregate shall conform M-12 B. 1.2. The shuttering to be provided shall be of ordinary timber planks and shall conform to M-26. 1.3. The dimensions of scantlings and battens shall conform to the design. The strength of the wood shall not be less than that assumed in the design. 2.0. General: 2.1. The designation ordinary M-100, M-150, M-200, M-250. specified as per I.S. Corresponding approximately to 1:3:6, 1:2:4, 1:1/2:3 and 1:1:2 nominal mix of ordinary concrete by volume respectively. 2.2. The ingredients required for ordinary concrete containing one beg of cement of 50 Kg. By weight (0.0342 Cu. M.) for different proportions of mix shall be as under: Grade of Total quantity of dry Proportion of fine aggregate Quantity of concrete aggregate by volume to coarse aggregate water per 50 per 50 Kgs. Of cement Kgs. Of to be taken as the sum cement of individual volume of maximum. fine and coarse aggregates, maximum M-100 (1:3:6) 300 Liters Generally 1:2 for fine 34 Liters M-150 (1:2:4) 220 “ aggregate to coarse aggregate 32 “ M-200 (1:1 ½:3) 160 “ by volume but subject to and 30 “ M-250 (1:1:2) 100 “ upper limit of 1:1 ½ and lower 27 “ limit 1:3 2.3. The water cement ratios shall not more than those specified in the above table. The cement content of the mix specified in the Table shall be increased if the quantity of water in a mix has to be increased to overcome the difficulties of placement and compaction so that the water-cement-ratio specified in the Table is not exceeded. 2.4. Workability of the concrete shall be controlled by maintaining a water-cement-ratio that is bound to give a concrete mix which is just sufficiently wet to be placed and compacted without difficulty with the means available. 2.5. The maximum size of coarse aggregate shall be as large as possible with in the limits specified but in no case greater than one fourth of the minimum thickness of the member, provided that the concrete can be placed without difficulty so as to surround all reinforcement thoroughly and to fill corners of the form. 2.6. For reinforced concrete work, coarse aggregate having a nominal size of 20 mm. are generally considered satisfactory. 2.7. For heavily reinforced concrete members as in the case of ribs of main beams, the nominal maximum size of coarse aggregate should usually be restricted to 5 mm. less than the minimum clear distance between the main bars, or 5 mm. less than the minimum cover to the reinforcement whichever is smaller. 2.8. Where the reinforcement is widely spaced as in solid slabs, limitations of size of the aggregate may not be important and the nominal maximum size may sometimes be as great as or greater than the minimum cover. 2.9. Admixture may be used in concrete only with approval of Engineer-in-charge based upon the evidence that with the passage of time, neither the compressive strength of concrete is reduced nor are other requisite qualities of concrete and steel impaired by the use of such admixtures. 2.10. The form work shall conform to the shape lines and dimension as shown on the plans and be so constructed as to remain sufficiently rigid during the placing and compacting of the concrete. Adequate arrangements shall be made by the contractor to safe-guard against any settlement of the form work during the course of concreting and after concreting. The form work of shuttering, centering, scaffolding bracing etc. shall be as per design. 2.11. Cleaning & Treatment of forms: 2.11.1.All rubbish, particularly chippings shaving and saw dust shall be removed from the interior of the form before the concrete is placed and the form work in contact with concrete shall be cleaned and thoroughly Page 2 of 88 wetted or treated. The surface shall be then coated with soap solution applied before concreting is done, Soap solution for the purpose shall be prepared by dissolving yellow soap in water to get consistency of paint. Alternatively a coat of raw linseed oil or form oil of approved manufacture may be applied in case steel shuttering is used. Soap solution or raw linseed oil shall be applied after thoroughly cleaning the surface. Care shall be taken that the coating does not get on construction joint surface and reinforcement bars. 2.12. Stripping time: 2.12.1. In normal circumstances and where ordinary cement is used forms may be struck after expiry of following periods.: (a) Sides of walls columns and vertical faces of beam 24 to 48 hours. (b) Beam soffits. (Props left under) 7 days. (c) Removal of props slabs (i) Slabs spanning up to 4.5 m. 7 days. (ii) Spanning over 4.5 mm. 14 days. (d) Removal of props to beams and Arches (i) Spanning upto 6 m. 14 days. (ii) Spanning over 6 m. 21 days. 2.13. Procedure when removing the form work: 2.4.1. All form work shall be removed without such shock or vibrations as would damage the reinforced concrete surface. Before the soffit form work and struts are removed, the soffits and the concrete surface shall be exposed where necessary in order to ascertain that the concrete has sufficiently hardened. 2.14. Centering: 2.14.1. The centering to be provided shall be got approved. It shall be sufficiently strong to ensure absolute safely of the form work and concrete work before, during and after pouring concrete. Watch should be kept to see that behavior of centering and form work is satisfactory during concreting. Erection should also be such that it would allow removal of forms in proper sequence without damaging either the concrete or the forms to be removed. 2.14.2.The props of centering shall be provided on firm foundation or base of sufficient strength to carry the loads without any settlement. 2.14.3.The centering and form work shall be inspected and approved by the Engineer-in-charge before concreting. But this will not relieve the contractor of his responsibility for strength, adequacy and safety of form work and centering. If there is a failure of form work or centering, contractor shall be responsible for the damages to the work, injury to life and damage to property. 2.15. Scaffolding: 2.15.1.All scaffolding, hoisting arrangements and ladders etc. required for the facilitating of concreting shall be provided and removed on completion work by contractor at his own expense. The scaffolding, hoisting arrangements and ladders etc. shall be strong enough to to act and shall be subject to the approval of the Engineer-in-charge. However, contractor shall be solely responsible for the safety of the scaffolding, hoisting arrangement, ladders, work and workman etc. 2.15.2. The scaffolding, hoisting arrangements and ladders shall allow easy approach to the work spot and afford easy inspection. 2.15.3. The rate is applicable to all conditions of working and height upto 4 mts. The rate shall include the cost of materials and labour for various operations involved such as: (a) Splayed edges, notching, allowance for overlaps and passing at angles, battens centering, shuttering, strutting, propping bolting, nailing, wedging, easing, striking and removal. (b) Filleting to form stop chamfered edges or splayed external angles not exceeding 20 mm. widths to beams, columns and the like. (c) Temporary opening in the forms for pouring concrete, if required, removing rubbish etc. (d) Dressing with oil to prevent adhesion of concrete with shuttering, and (e) Raking or circular cutting. 2.16. Re-Use: 2.16.1. Before-re-use, all forms shall be inspected by Engineer-in-charge and their suitability ascertained. The forms shall be scarred, cleaned, and joints gone over, repaired where required. Inside surface shall be retreated to prevent adhesion of concrete. 2.0 General: 2.1. The relevant specifications of item No. 5.4.1. of ordinary concrete shall be followed except that the concrete mix shall be designed from preliminary tests, the proportioning of cement and aggregates shall be done by weight and necessary precautions shall be taken in the production to ensure that the required work cube strength is attained and maintained. The controlled concrete shall be in grades of M-100, M- 150, M-200, M-250, M-300, M-350, & M-400, with prefix controlled added to it. The letter ‘M’ refers to mix and numbers specify 28 days works cube compressive strength of 150 mm. cubes of the mix expressed in Kg./Cmt. Page 3 of 88 2.2. The proportion of cement, sand and coarse aggregates shall be determined by weight the weight batch machine shall be used for maintaining proper control over the proportion of aggregates as per mix design. The strength requirements of different grade of concrete shall be as under: Grade Of Concrete Compressive strength of 15 cms. Cubes in Kg./Cmt. At 28 days, conducted in accordance with I.S. 516-1959. Preliminary test Min. Work test Min. M-150 200 150 M-200 260 200 M-250 320 250 M-300 380 300 M-350 440 350 M-400 500 400 In all cases, the 28 days compressive strength specified in above table above be the criteria for acceptance or rejection of the concrete. Where the strength of a concrete mix as indicated by tests, lies in between the strength of any two grades specified in the above table, such concrete shall be classified in for all purposes as concrete belonging to the lower of the two grades between which its strength lies. 3.0 Workmanship: 3.1. The proportions for ingredients chosen shall be such that concrete has adequate workability for conditions prevailing on the work in question and can be properly compacted with means available except where it can be shown to the satisfaction of the Engineer-in-charge, that the supply of properly graded aggregate of uniform quality can be maintained till the completion of work. Grading of aggregate shall be controlled by obtaining the coarse aggregates, in different sizes and being in them in the right proportions as required. Aggregate of different sizes shall be stocked in separate stock piles. The required quantity of material shall be stock piled several hours, preferably a day before use. The grading of coarse and fine aggregate shall be checked as frequently as possible, the frequency for a given job being determined by the Engineer-in- charge to ensure that the suppliers are maintaining the uniform grading as approved for samples used in the preliminary tests. 3.2. In proportioning concrete, the quantity of both cement and aggregate shall be determined by weight. Where the weight of cement is determined by accepting the maker’s weight per bag a reasonable number of bags shall be weighted separately to check the net weight. Where cement is weighted from bulk stocks at site and not by bags, it shall be weighted separately from the aggregates. Water shall either be measured by volume in calibrated tanks or weighed. All measuring equipments shall be maintained in clean and serviceable condition. Their accuracy shall be periodically checked. 3.3. It is most important to keep the specified water cement ratio constant and at its correct value. To this end, moisture content in both fine and coarse aggregates shall be determined by the Engineer-in-charge, according to the weather conditions. The amount of mixing water shall then be adjusted to compensate for variations in the moisture content. For the determination of moisture content in the aggregates, I.S. 2389 (Part-III) shall be referred to. Suitable adjustments shall also be made in the weights of aggregates due to variation in their moisture content. Minimum quantity of cement to be used in concrete shall not be less than 220 Kg./M 3 in plain concrete and not less than 250 Kg/M3 in reinforced concrete. 4.0. Mode of measurement and payment: 4.1 The rate shall be for a unit of one cubic meter. SPECIFICATION – 9 (Item No : 16) Providing and laying cement concrete 1 : 2 : 4 (1 cement : 2 coarse sand : 4 stone aggregates 20mm nominal size) 100mm thick as PLINTH PROTECTION as per detailed drg. including cost of excavation, sand filling and pcc finishing top surface with neat cement slurry including making false square of 300 X 300 mm size and curing including cost of form work but excluding cost of reinforcement etc. complete as directed by E. I. C. 1.0. Materials 1.1 Water shall conform to M-1, sand shall conform to M-6, and Cement shall conform to M-3 stone aggregate 40 mm nominal size shall conform to M-12 2.1 Relevant specifications of item shall be followed except that cement concrete shall be mixed in the proportion of 1:4:8 by volume. 2.0. Workmanship But the proportion of mix will be nominal and the ratio of fine and coarse aggregate may be slightly adjusted with in limits keeping the total volume of aggregates to a given volume cement constant, to suit the sieve analysis of the aggregates. Cement shall on no account be measured by volume, both it shall always be used directly from the bags (i.e., 50 Kg/bag). Page 4 of 88 The proportion of cement, sand, aggregate for concrete of proportion 1:4:8, 1:3:6, 1:2:4 by volumes shall generally consist of quantities as given below: The quantity of water used shall be such as to produce concrete of consistency required by the particular class or work and shall be decided by the use of slump cone. Sufficient care should be taken to see that no excess quantity of water is used. The final proportion of the aggregates and the quantity of water shall be decided by the Engineer on the basis of test in each case. The slum shall be specified for each class of work and shall in general be as follows:- Type of Concrete Mix slump (Millimetres) Mass Concrete 50 Roads and pavements, hand finished 100 Roads and pavements, machines finished 25 Floor paving 50 All plain concrete shall be preferably mixed in a drum type power driven machine with a loading hopper, which will permit the accurate measure of various ingredients. If hand mixing is authorized, it should be done on a watertight platform. The mixing of each batch in the concrete mixer shall continue for not less than 2 minutes after the materials and water are in the mixer. The volume of mixed materials per batch shall not exceed the manufacturer’s rated capacity of the mixer. The mixer shall rotate at a peripheral speed of about 60 metres per minute. Concrete shall be poured and consolidated in its final position with in half an hour of mixing. The re-tempering of concrete, which has partially hardened, that is remixing with or without additional cement, aggregate or water shall not be permitted. Concrete in c.c. 1:2:4 will be required to be vibrated if specified and directed by the Engineer. In case if the thick\ness of concrete is more than 150 mm in thickness, it may be vibrated if directed by the Engineer. 3.0 Mode of measurements and payment 3.1 The concrete shall be measured for its length and breadth, limiting dimensions to those specified on plan or as directed. 3.2 The item with all respect, the payment shall be made on Square Meter basis and measurement shall be taken as per the clear inside length and breadth of actual treatment area. SPECIFICATION – 10 (Item No : 29) Providing and laying polished 18 mm thk telephone black granite stone slab flooring over risers & treads of steps with nosing/ moulding with anti skid grooves over 20mm (average) base of cement mortar 1:4 (1 cement : 4 coarse sand) and jointed with grey cement slurry including rubbing, curing, moulding and polishing to edge to give high gloss finish etc. complete. 1.0. Materials: 1.1 Water shall confirm to M-1. 1.2 Granite stone slab 18mm thick shall conform to M-52 . 1.3 Cement Mortar shall conform to M-11. 2.0. Workmanship: Granite slab/stone shall be machine cut free edges with half round, double polished colour shall be fixed in true line and level finished tread and rise in one piece partition for urinals shall be fixed in wall with cement mortor (1:3). If required necessary supports shall be provided to maintain true line and level with curing etc. Page 5 of 88 2.1 Each slab shall be cut to the required size and shape and fine chisel dressed at all the edges. The sides thus dressed shall have a full contact if straight edges is laid along. The sides shall be table rubbed with coarse and before paving. All angles and edges of the slabs shall be square and free form chippings and giving aplane surface. The thickness shall be 18 mm (average) at any place of the slab. 2.2 Bedding for the granite stone slab shall be cement mortar 1:4 (1 cement: 4 sand) of avg. thickness 18 mm as given in the description of the item sub grade shall be cleaned wetted and mopped. Mortar of the specified mix and thickness shall be then be spread on an area sufficient to receive one granite stone slab. The slab shall be washed clean before laying. It shall be laid on top pressed, tapped gently to bring it in level with the other slabs. It shall them be lifted and laid aside. Top surface of the mortar shall then be of honey like consistency shall be applied. The slab shall then be allowed to harden bit. Over this surface, cement slurry of honey like consistency shall be applied. The slab shall then be gently placed in position and taped with wooden mallet till it is a properly shall enter not less than 10 mm under the plaster, skirting or dado. The junction between the wall floor shall be finished neatly. The finished surface enter not less than to levels and slops as directed. 2.3 The floor shall be kept wet for a minimum period of 7 days, so that bedding and joints set properly. Mode of Measurement 3.1 The floors, riser, tread etc. shall be measured by in sq. mtr. Length shall be measured along the finished faces. Height shall be measured from finished level of floor to top. 3.2 The rate shall be for a unit of one sq. mtr. SPECIFICATION – 11 (Item No : 30) Providing and fixing 18 mm thick black telephone granite top and sides sandwitch type platform over rough kota stone slab jointed by CM 1:4 ( 1 cement : 4 coarse sand ) in vertical and horizontal support with front facia with 1.5 inch thick front moulding edges, polishing, incl. cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 hand broken aggregate 40 mm Nominal size ) for support of granite slab including cutting holes for table top wash basin & kitchen sink and curing etc. comp. as directed by engineer-in-charge. 1.0 Materials: - 1.1 Black Granite Slab shall confirm to M-52 1.2 Polished kota stone shall confirm to M-49 1.3 Cement shall confirm to M-3 1.4 White Cement shall confirm to M-4 1.5 Sand shall confirm to M-6 1.6 Stone Grit shall confirm to M-8 1.7 Clair Counter Top Wash Basin (Cera, Jaquar or equivalent ) 1.8 Central hole CP basin mixer with popup waste with 450 mm long braided hoses ( Jquar or equivalent make) 1.9 Chromium plated bottle trap with necessary coupling as per manufacturer’s specifications 2.0 CP brass waste for wash basin- 40 mm dia as per manufacturer’s specifications 2.0 Workmanship: 2.1 Work shall be carried out as per design and drawings given by engineer in-charge. 2.2 18 mm black granite slab & 25 mm thick kota stone shall be used for top, bottom & supports using CM 1:4 ( 1 cement : 4 coarse sand ). Cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 hand broken aggregate 40 mm nominal size ) shall be done between black granite & kota stone for top platform. 2.3 Front facia with moulding edges, polishing shall be done as per drawings given by engineer-in-charge & the final joints shall be filled by white cement. 2.4 For fixing wash basin specification no.23.127 of General Specifications for Building works shall be followed. 3.0 Mode of Measurement & Payment: - 3.1 The work shall be measured on sq.mt basis and including all materials and labour etc, complete. The rate shall be for a unit of one Square Metre. SPECIFICATION – 12 (Item No : 31) Providing and fixing 25 mm THICK telephone BLACK GRANITE PATTI as a frame of WINDOW & VENTILATOR including moulding of projected exposed faced, laid on 10 mm thick cement mortar 1:3 (1:cement 3:sand) and jointed with grey cement slurry including rubbing & polishing etc . Item includes thick groove all around window/ door opening, complete as per E.I.C. Materials : 1.0. Materials: Page 6 of 88 1.1 Water shall confirm to M-1. 1.2 Granite stone slab 25mm thick shall conform to M-52 . 1.3 Cement Mortar shall conform to M-11. 2.0. Workmanship: Granite slab/stone shall be machine cut free edges with half round, double polished colour shall be fixed in true line and level finished tread and rise in one piece partition for urinals shall be fixed in wall with cement mortor (1:3). If required necessary supports shall be provided to maintain true line and level with curing etc. 2.1 Each granite stone shall be cut to the required size and shape and fine chisel dressed at all the edges. The sides thus dressed shall have a full contact if a straight edges is laid along. The sides shall be table rubbed with coarse and before paving. All angles and edges of the slabs shall be tue square and free form chippings and giving aplane surface. The thickness shall be 12 mm (average) at any place of the slab. 2.2 Bedding for the granite stone sill shall be cement mortar 1:3 (1 cement : 3 sand) of given in the description of the item sub grade shall be cleaned wetted and mopped. Mortar of the specified mix and thickness shall be then be spread on an area sufficient to receive one granite stone sill. The granite stone shall be washed clean before laying. It shall be laid on top pressed, tapped gently to bring it in level with the other slabs. It shall them be lifted and laid aside. Top surface of the mortar shall then be of honey like consistency shall be applied. The slab shall then be allowed to harden bit. Over this surface, cement slurry of honey like consistency shall be applied. The slab shall then be gently placed in position and taped with wooden mallet till it is a properly shall enter not less than 10 mm under the plaster, skirting or dado. The junction between the wall floor shall be finished neatly. The finished surface enter not less than to levels and slops as directed. 2.3 The floor shall be kept wet for a minimum period of 7 days, so that bedding and joints set properly. 3.0. Mode of measurement 3.1 The Sills, Jambs etc. shall be measured by in sq.metre. length shall be measured along the finished faces. Height shall be measured from finished level of floor to top. Lining of pillars shall be measured under this them 3.2 The rate shall be for a unit of Square Metre. SPECIFICATION – 13 (Item No : 32) Providing & fixing both face polished KOTA STONE slabs 25mm thick in urinal partition & platform etc., including cutting edges moulding, polishing etc.,…. As per details & directed by E.I.C. 1.0 Materials: - 1.1 Water shall confirm to M-1. 1.2 Polished kota stone shall confirm to M-49 1.3 Cement shall confirm to M-3 1.4 Sand shall confirm to M-6 1.5 Stone Grit shall confirm to M-8 2.0. Workmanship: Granite slab/stone shall be machine cut free edges with half round, double polished colour shall be fixed in true line and level finished tread and rise in one piece partition for urinals shall be fixed in wall with cement mortor (1:3). If required necessary supports shall be provided to maintain true line and level with curing etc. 2.1 Each kota stone shall be cut to the required size and shape and fine chisel dressed at all the edges. The sides thus dressed shall have a full contact if a straight edges is laid along. The sides shall be table rubbed with coarse and before paving. All angles and edges of the slabs shall be tue square and free form chippings and giving aplane surface. The thickness shall be 25 mm (average) at any place of the slab. 3.0 Mode of measurement 3.1 The rate shall be for a unit of Square Metre. SPECIFICATION – 14 (Item No : 34) Providing, laying & fixing BRICK TILES (slate tiles) 15"x 8" (Asian, Somani or equivalent make) tiles over 10mm (average) thick base of CM 1 : 3 (1 cement : 3 sand) laid over and jointed with neat grey cement slurry including filing the joint with white / colour cement , complete in true line and level / slope, cleaning & rubing, as per approved pattern as per detailed drawing all lvl. at all height & lvl. as directed by E.I.C. 1.0 Materials: 1.1 Water shall be confirm to M–1 of specification booklet of tender. 1.2 Cement mortar shall be confirm to M–11 of specification booklet of tender Page 7 of 88 1.3 10 mm thick brick tiles 15” X 8” confirming to IS : 15622 shall be of shade approved by Engineer in charge. The tiles shall be hard, even / sound 1 regular in shape and uniformly colored. It shall be without any soft veins and cracks of flow. The size of the tile shall be as per drawings or otherwise specified by Engineer in charge. 2.0 Workmanship: 2.1 Each brick tiles side cut to the required size and shape as shown In the working drawing supplied by Engineer in charge. All angles and edges of tiles shall be True Square and free from chipping and giving a plain surface. The shade and quality of brick tiles shall be got approved by Engineer in charge. 2.2 Tiles shall be fixed in 10 mm thick cement plaster in CM 1: 3 (1 Cement : 3 Sand) of grey thickness as given in the description of the item sub grade shall be cleaned wetted and mopped. Motor of the specified mix and thickness shall be than spread on the area. The tiles shall be washed clean before laying. It shall laid on top pressed tapped gently to bring it in with the adjoining stone skirting. The top surface of mortar shall be corrected by adding fresh motor of hollow and depressions. The mortar shall than be allowed to harden bit over the surface cement slurry of honey like consistence shall be applied The joint shall be as thin as possible. 3.0 Mode of measurement: 3.1 The rate includes the cost of all materials and labour involved in all operations described above. Item shall be measured on SqM. basis. SPECIFICATION – 15 (Item No : 35) Providing and fixing tiled roofing with manglore tiles with cement mortar (1:4 1,cement, 4-sand) as per direction engineer in charge. 1.0 Materials: 1.1 Water shall be confirm to M–1 of specification booklet of tender. 1.2 Cement mortar shall be confirm to M–11 of specification booklet of tender 1.3 The tiles shall be hard, even / sound 1 regular in shape and uniformly colored. It shall be without any soft veins and cracks of flow. The size of the tile shall be as per drawings or otherwise specified by Engineer in charge. 2.0 Workmanship: 2.1 All angles and edges of tiles shall be True Square and free from chipping and giving a plain surface. The shade and quality of brick tiles shall be got approved by Engineer in charge. 2.2 Tiles shall be fixed in 10 mm thick cement plaster in CM 1: 4 (1 Cement : 4 Sand) of grey thickness as given in the description of the item sub grade shall be cleaned wetted and mopped. Motor of the specified mix and thickness shall be than spread on the area. The tiles shall be washed clean before laying. It shall laid on top pressed tapped gently to bring it in with the adjoining tile. The top surface of mortar shall be corrected by adding fresh motor of hollow and depressions. The mortar shall than be allowed to harden bit over the surface cement slurry of honey like consistence shall be applied. The joint shall be as thin as possible. 3.0 Mode of measurement: 3.1 The rate includes the cost of all materials and labour involved in all operations described above. Item shall be measured on SqM. basis. SPECIFICATION – 16 (Item No : 37) Providing and applying CHEMICAL WATER PROOFING TREATMENT the sunk area, including roughing cleaning the surface after applying internal waterproofing 2 coats of Sika® Latex Water Resistant Bonding Agent Spread cement primer by using Sika® Latex in Water = 1 : 4 by volume in order to obtain a thin layer. applying coat for water proofing on concrete and mortar structures to prevent water infiltration and dampness. including curing at with specified period as directed etc. complete as directed by E. I. C. 1.0 Material: - The cement shall confirm to M-3 (3.1 / P.9 / V.1), water shall confirm to M-1 (1.1 to 1.5 / P.9 / V.1), sand shall confirm to M-6 (6.1 to 6.3 / P.9,10 / V.1), water proofing compound shall brick bats shall confirm to M-14 (14.1 to 14.2 / P.12 / V.1) 2.0 Workmanship: - The work shall be carried out as per general instruction given by the Engineer in charge. The water proofing treatment to the terrace shall be laid directly on the R.C.C. base slab in betting with cement solution of water proof compound as and where found necessary for filling the honey combs. Surface shall fully be covered with joint less water proof ¾ thick cement plaster finished smooth with trowel color cement and shall be marked in 0.30m x 0.30m False square. 3.0 Mode of measurement and payment:- The rate incl. all the material and labour involved in the satisfactory completion of work. Page 8 of 88 The item with all respect, the payment shall be made on square meter basis and measurement shall be taken as per the clear inside length and breadth from parapet wall and average over finishing floor as breadth. A guarantee bond of ten years guarantee requisite stamp paper shall be given by the contractor to the department. Any defect will be observed later on, shall be rectified by the contractor at his own risk and cost. Contractor shall be bound to carry out all such rectification work without claming any extra. The rate shall be unit for a one square meter. SPECIFICATION – 17 (Item No : 40) Providing, applying & Finishing wall with EXTERIOR TEXTURED PAINT - APEX ULTIMA WEATHER PROOF EMULSION PAINT of approved shade over prepared surface which includes rubbing scraping with emery stone, applying one coat of primer over which 2 coats of paint tobe applied to get desired finish; shade approved by E.I.C. including cleaning etc. & as per E.I.C. direction. 1.0 Material:- The water shall conform to M-1 APEX paint shall conform to I.S. 2.0 Workmanship:- Preparation of surface: The surface shall be thoroughly cleaned of all dust, dirt, mortar droppings and other foreign matter before APEX paint I to be applied. Oil or grease spots shall be removed by suitable chemical and smooth surface shall be rubbed with wire brushes. All round portion of the surface plaster shall be removed to full depth of plaster in rectangular patches and plastered again after raking the masonry joints properly. Such portion shall be wetted and allowed to dry. All unnecessary nails shall be removed; holes, cracks, patches etc. shall be made good with material similar in composition to the surface to be prepared. 3.0 Scaffolding:- Wherever scaffolding is necessary, it shall be erected in such a way that so far as possible no part of scaffolding shall rest on the surface to be colored. A properly secured strong and well-tied suspended platform (Zoola) may be used for colored work. When ladders are used pieces of old gunny bags shall be tied at top and to bottom to prevent scratches to the floors and wall. For color work of ceilings, proper tage scaffolding shall be erected where necessary. 4.0 Application of paint:- No painting shall be done when the paint is likely to be exposed to a temperature below 7˚ C within 48 hours after application. When weather condition are such as to cause be carried out "in the shadow " as far as possible. This helps the proper hardening of the paint film by keeping the surface more for a longer period. To maintain the uniform mixture and to prevent segregation, the paint shall be stirred frequently in the bucket. For undecorated surface, the surface shall be treated with minimum two coats of APEX paint. Not less than 24 shall not be allowed between two coats. Next coat shall not be started until the proceeding coat has become sufficiently hard to resist marking by the brush being used, In hot dry weather, the proceeding coat shall be slightly moistened before applying the subsequent coat. The finished surface shall be even end uniform in shade without patches, brush mask, paint drops etc. The cement paint shall be applied with a brush with relatively short stiff hog or fiber bristles. The paint shall be brushed in uniform thickness and shall be well brushed out. Weather proof exterior emulsion paint shall not be applied on surface already treated with white wash, color wash, distemper dry or oil bound varnishes, paint etc. such surface shall be scrapped first and prepared for application of paint as per manufacturers specifications. 5.0 Mode of measurement and payment:- All the work shall be measured in the decimal system as under: Dimensions shall be measured to nearest 0.01 M. Area in individual items shall be worked out to the nearest 0.01Sq.mt. All the works shall be measured in Sq. m. Deductions for jambs, soffits, sills etc. not exceeding 0.5 sq. m. each in area, for ends of joists, posts, beams, girders, steps etc. not exceeding 0.5 sq. m. each in area and for opening exceeding 0.5 sq. m. not exceeding 3.0 sq. m. each in area. Deduction and additions shall be made as under: No deduction shall be made for ends of joists, beams, posts etc. and openings not exceeding 0.5 sq. m. each. No addition shall be made for reveals, jambs, soffits, sills etc. of these openings or for finish around ends, joists, beams, posts etc. Deduction for opening 0.5 sq. m. but not exceeding 3 sq. m. each shall be made as follows and no addition shall be made for reveals, jambs, soffits etc. of these openings. When both the faces of walls are provided with finish, deduction shall be made for one face only. Page 9 of 88 When each face of wall is provided with a different finish, deduction shall be made for that side frame for door, window etc. on which width of reveals is less than that of the other side. When widths of reveals on both faces of wall are equal, deduction of 50 % of area of opening on each face shall be made from total area of finish. When only one face of wall is treated and the other face is Not treated, full deduction shall be made if the width of reveal on the treated side is less than that on the untreated side, but if the width of the reveal is equal or more than on the untreated side neither deduction for additions to be made for reveals, jambs, soffits, sills etc. 4. In case of area of opening exceeding 3 sq. m. each, deduction shall be made for opening but jambs, soffits, sills shall be measured. 5. No deduction shall be made for attachment such as casing, conducts, pipe, electric wiring and the like. 6. Corrugated surfaces shall be measured flat as fixed and not girth. The quantities so measured shall be increased by the following percentage and the resultant shall be included with the general areas: (a) Corrugated steel sheets 14% (b) Corrugated A.C. sheets (With rolls) 10 % (c) Semi corrugated A.C. sheets 10 % (d) Nainital pattern roof (plain sheeting W.) 20 % (e) Nainital pattetn roof (with corrugated sheet) 25 % 7. Cornices and other wall features, when they are not picked out in a different finish / color shall be girthed and included in the general area. 8. The rate shall include the cost of all materials, labor, scaffolding, Protective measures etc. involved in the operations described above. 9. The rate shall be for a unit of one SqM. SPECIFICATION – 18 (Item No : 42) Providing & Fixing Full glass door with floor hinges, 12mm toughened glass of Saint Gobain is used for glass door with decorative etching works in glass with necessary fixtures & fittings. The item includes both side fixed glasses. The specification of fixed glass is same as in glass door. 1.0 Material:- 1.1 Glass shall be confirm to M–38 of specification booklet of tender. 2.0 Workmanship:- 2.1 All glass shall be of standard architectural grade, free of cracks. 2.2 Each glass shall be cut to the required size and shape. 2.3 The work shall be carried out in best workman like manner. 3.0 Mode of measurement and payment:- 3.1 The rate shall be for a unit of one SqM. SPECIFICATION – 19 (Item No : 44) Providing and fixing NCL ALLTEK Fully Composite Sliding WINDOWS, fabricated from roll formed sections made of Galvanized Steel Colour Coated/ Powder Coated (Base Steel as per IS 513 “D” quality, Galvanized as per IS 277 with Zinc of 120 grams/ Sqr. Mtr.) with total coated thickness of 0.60 mm Section for external frame bottom should be of 68 x 25mm (Allumin) , External frame sides & Top should be of 68 X 25mm(Allumin), Section for shutter should be of 60 x 23mm, and Lap Strip should be of 30 x 7.5mm(uPVC). The Frame Section should be cut to length and mitre joined with L- Bracket & Shutter Sections should be cut to length and mitre joined with Corner Bracket. Ethyl Propylene Diamine Monomer (EPDM) Gasket should be used all around glass in shutter. Corner bracket for External frame made of Al ‘L’- angle, Corner Bracket for Internal frame made of Polypropylene, Crescent Latch, Rollers, & EPDM Gaskets for shutters, wool pile for lap strip, Bump Stop Base & Rubber for shutter stopper. Glass shutter and fixed glass portions should be provided with a glass of 4 mm thick Plain Glass of Saint-Gobain/Modi-Guard or colour of the glass & make approved as directed by architect. Material & Workmanship: Commercial Section of Alluminium 68mm x 25mm thick with sliding shutter. Section for shutter should be of 60 x 23mm, and Lap Strip should be of 30 x 7.5mm(uPVC). Glass of 4 mm thick transeperant plain glass of saint globain. All Accessories and hardware and gasket etc. Mode of Measurement and pament: The rate including all the material and labour involved in the satisfaction completion of work. The rate is inclusive of providing and fixing all necessary fixture and fastening like screws, Adhesive, chips beadings etc complete the item to the satisfaction of engineer in charge. The rate shall be for a unit of SqM. Page 10 of 88