P.O. Box 85518 Lincoln, NE 68501-5518 CHANGE SERVICE REQUESTED March 27, 2009 Volume 31 Number 11 www.processor.com Products, News & Information Data Centers Can Trust. Since 1979 In This Issue... Cut HVAC Key Points COVER FOCUS Saving Power In Your Data Center (cid:127) Get an idea of where you stand by taking advantage of vendors’ offers for free Where can your data center save money by reducing the Power Usage assessments and audits. amount of power it uses related to cooling, outdated (cid:127) Badly placed power strips, UPSes, and equipment, storage, and the desktop? We talked with cables can cause hot spots and drive up experts to find out. cooling needs, so carefully shift your equip- Cut HVAC Power Usage................................................1 ment to improve airflow. Save Data Center Power By Updating Equipment........7 (cid:127) Use fewer devices closer to their rated Scale Back Storage Power............................................8 Streamline Your Cooling & Airflow Setups capacity to boost efficiency and reduce Desktop Power Savings ................................................9 & Save Money At The Same Time wasted energy. Data Center Sourcing Options by Carmi Levy Get An Energy Audit Lease. Outsource. Cloud computing. (cid:127) (cid:127) (cid:127) Which option is the best for your AS BELTS TIGHTEN and budgets An audit identifies where enterprise? Special coverage shrink, CIOs and IT directors your HVAC infrastructure begins on page 24. are scouring every last line item works and where it doesn’t. for inexpensive fixes and major Beyond helping find hot spots savings. The data center’s elec- and potential trouble areas, it tricity bill has emerged as a also lays the groundwork for major target of opportunity. data center managers to educate You don’t need to rip out and themselves about power man- TECH & TRENDS replace your equipment to drive agement best practices. Most efficiencies in power and cool- vendors these days provide ■Market inertia and convention are no reason to over- ing. Often, the savings are right basic audits at no cost. look the potential benefits that flywheel UPS systems under your nose. could offer your organization now........................page 1 “The impact of the economic Manage Your Airflow & Eliminate Obstructions ■Aside from costing an organization millions, the loss- downturn is really twofold,” says Tim Hirschenhofer, dir- “The immediate knee-jerk es a company can incur through data breachesrisk ector of sales for Degree Con- reaction to a thermal problem is damaging its brand, squandering customer confidence, trols’ AdaptivCool division to add more cooling equip- incurring regulatory fines, and racking up legal fees, (www.adaptivcool.com). “Cus- ment,” says Hirschenhofer. “But among other concerns........................................page 32 tomers want to save money, and the reality is that most data ■A recent survey conducted by BeyondTrust, a devel- certainly controlling airflow and centers today have more than oper and marketer of least privilege management soft- HVAC costs are the easiest ways enough cooling to handle the ware, reveals that 92% of critical vulnerabilities report- to gain efficiencies in the data heat load that they’ve got.” ed by Microsoft last year could have been prevented center. This approach also ex- Airflow distribution is critical simply by removing administrator rightsfrom tends the life of existing data centers by Here are a few suggestions to get you to getting the cold air where it’s needed and Windows users................................................page 33 allowing more equipment to be put into the started on scaling back your HVAC power in the right amount, he says. By actively same size facility.” consumption. Go to Page 6 NEWS ■IBM is reportedly in talks with Sun Microsystems Are Flywheels For You? Of Special Interest To: ✘ regarding a potential acquisition, according to The Health ■ Wall Street Journal................................................page 2 Education ■ Government ■ ■Large enterprises will be able to lease Microsoft softwareat a discount of up to 26%....................page 2 ■The economic downturn is propelling a surge in the Data Centers Could Benefit Key Points acquisition of Linuxamong manufacturers, financial From Kinetic Energy Devices services, government agencies, and retail industries, (cid:127) Flywheels store kinetic energy that can according to IDC ..................................................page 2 by William Van Winkle motor cuts out, a flywheel-based, online convert instantly into electrical energy ■Microsoft now has until April 21 to respond to allega- (cid:127) (cid:127) (cid:127) UPS uses the flywheel’s stored kinetic ener- when employed in an online UPS product tions that it unfairly stifles competition by bundling its INERTIAISTHECENTRALPRINCIPLEbehind gy as the basis for generating electricity. The with much greater reliability than battery- Internet Explorersearch engine with the company’s flywheel technology. It may also be the UPS itself is a generator. This generation based UPS systems. Windows software................................................page 3 central reason why chemical battery-based sucks energy out of the system, but there’s (cid:127) The environmental benefits of flywheel ■A two-year study by the Kauffman Foundation found UPSes have been the predominant backup enough energy there to result in a few min- technology vs. battery are legion, from approach for SME data centers over the last utes of runtime in a properly sized system. superior power efficiency to the elimination that many high-tech worker immigrants contributed three decades. But market inertia and con- A traditional generator, like the ones of toxic chemical containment and disposal. greatly to the U.S. economy by cofounding a quarter of vention are no reason to overlook the waiting around to kick in and power your (cid:127) Despite the higher up-front costs of fly- tech and engineering startups..........................page 9 potential benefits that flywheel UPS sys- data center after a sustained loss of power, wheel systems, there are many ways in ■Internet Explorer 8 can be disabled in the Windows 7 tems could offer your organization now. converts fuel into mechanical energy, which the technology can more than pay Release Candidate, Microsoft has confirmed......page 32 which is then converted into electrical ener- for itself in a fairly short time. Flywheels At A Glance ■Revenue from blade serverswas up about 31% and gy. A battery-based UPS takes electrical A flywheel is a mechanical device that energy from the wall and stores it in chemi- shipments were up 30% during the fourth quarter of last The Battery Fallacy stores rotational energy. In modern data cen- cals, from which it can be extracted and year....................................................................page 36 ters, flywheels that are spun at a constant used again as electricity. The flywheel- The trouble for flywheels has always rate by a small motor can store enough ener- based UPS also takes electricity from the been that battery-based UPSes generally The Processor.com home page is frequently updated with gy to power large computer systems for wall, stores it as kinetic energy, then con- deliver 10 to 15 minutes of runtime. new articles and hardware news to help you keep current. short spans of time, just as chemical battery verts that kinetic energy into mechanical According to Gary Rackow, vice president Visit www.processor.com today. backups do. If the power to the flywheel’s energy and from that into electrical energy. Go to Page 6 Page 2 Processor.com March 27, 2009 Subscribe Today/Address Change Form For address change, fill out form below with new information and mail or fax. PLEASE PRINT What type of subscription request is this? ■■ New ■■ Renewal ■■ Cancel © Copyright 2009 Sandhills Publishing Company. Phone: ( ______ )________________________________ Fax: ( ______ ) __________________________________________ All rights reserved. Contact Name:__________________________________________________________________________________________ Company Name: ________________________________________________________________________________________ Subscriptions Address: ______________________________________________________________________________________________ Mail Form To: P.O. Box 85518 (cid:127) Lincoln, NE 68501-5518 Overnight Delivery: 120 West Harvest Drive (cid:127) Lincoln, NE 68521 City: ___________________________________________ State: ________ Postal Code:______________________________ (800) 819-9014 | LOCAL: (402) 479-2132 | FAX: (402) 479-2193 Country: ______________________________________________________________________________________________ Advertising & Reprints Email: ________________________________________ Web Address:____________________________________________ (800) 247-4880 | (402) 479-2141 | FAX: (402) 479-2193 1. What is the size of your company 3. What is your annual computer hardware/ Editorial Staff (how many employees)? software purchasing budget? [email protected] ■■ Less than 10 ■■ 200 to 499 ■■ $0 to $9,999 ■■ $100,000 to $249,999 (800) 544-1264 ■■ 10 to 99 ■■ 500 to 999 ■■ $10,000 to $24,999 ■■ $250,000 to $499,999 ■■ 100 to 199 ■■ 1,000+ ■■ $25,000 to $49,999 ■■ $500,000 to $999,000 ■■ $50,000 to $99,999 ■■ $1,000,000+ Do you have a new product that data center/IT managers would be interested in learning about? Call (800) 544-1264 2. How often do you purchase computer or email [email protected]. hardware/software? ■■ Weekly ■■ Quarterly ■■ Bi-weekly ■■ Annually ■■ Monthly ■■ No Involvement www.Processor.com News UpcomingITEvents Are you looking to learn more about data center ❙ ❙ or IT topics? Network with some of your peers? New Dow Candidates Study Shows Increase other Microsoft software. The move is seen Consider joining a group of data center Include Tech Companies In Computer Science Students as a bid by the software giant to retain its professionals. If you have an event you’d like to customers in the midst of a recession. list, please send an email to Google, Cisco, and Apple are among the names Student enrollment in computer science pro- [email protected]. being considered for possible inclusion in the grams is up 6.2% compared to last year when ❙ PCI Security Standards Council Dow Jones Industrial Average, according to looking at both premajors and majors, accord- Releases PCI DSS Checklist - MARCH - Reuters. The Dow, which serves as an indicator ing to the latest data from the Computing In an effort to help companies still not in com- AITP Akron of the stock market by tracking the stock prices Research Association. When looking at only pliance with the 12 security controls included March 31, 6 p.m. of 30 of the largest, most widely held compa- students who have declared a computer sci- in the PCI DSS (Payment Card Industry Data Lindsay’s Amber Restaurant nies, has lost 25% of its value so far this year, ence major, the number is up 8.1% from a 1500 Canton Road Security Standard), the PCI Security Stan- prompting calls for changes in the companies it year ago. Computer science bachelor degree Akron, Ohio dards Council has released “The Prioritized tracks, Reuters reports. Citigroup and General production is expected to be down 10% this www.akron-aitp.org Approach To Pursue PCI DSS Compliance,” Motors are two of the companies that will likely year, compared to a decline of about 20% last a document that outlines six milestones com- - APRIL - be removed from the Dow, as their stock prices year. The number of new computer science panies can use as a road map to gaining com- AFCOM Omaha have dropped below $2. Ph.D. students is also on the rise, up 10% April 1 pliance. The PCI DSS, which aims to secure ❙ compared to last year’s figures. The Comput- Mutual Of Omaha IBM Could Buy Sun Microsystems credit and debit card data, has left many com- ing Research Association study notes that 3300 Dodge St. panies overwhelmed and uncertain as to Omaha, Neb. IBM is reportedly in talks with Sun Microsys- diversity in the undergraduate programs where to start to reach compliance. As further www.afcomomaha.org tems regarding a potential acquisition, accord- remains poor, with only 11.8% of computer assistance, the council released a spread- (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) ing to The Wall Street Journal.The deal could science degrees awarded going to women AFCOM Central Ohio sheet-based utility that will help companies be worth at least $6.5 billion, according to the and 64.1% going to recipients who reported April 8, 11:30 a.m. plot their progress in achieving the milestones report, which represents a 100% premium their ethnicity as white. Liebert and help auditors view the compliance status- 1050 Dearborn Drive over Sun’s stock price when reports of the ❙ Microsoft Offers es of companies. Columbus, Ohio acquisition were made public. According to the www.afcomcentralohio.org Journal, the two companies share many simi- Discounted Software Leasing ❙ Recession Spurs Linux Adoption (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) larities: Both make computer systems for the Thanks to new price cuts AITP Central Idaho The economic downturn is propelling a “surge non-Windows market, support Linux and Java offered by Microsoft, April 8, 11:45 a.m. in the acquisition of Linux” among manufac- Owyhee Plaza Hotel open-source software, and aren’t as dependent large enterprises turers, financial services, government agen- 1109 Main St. on Intel microprocessors as other manufactur- and other organi- cies, and retail industries, according to an Boise, Idaho ers. Sun has reportedly been looking for a zations will be www.boisestate.edu/dpma IDC survey conducted last month. Among the potential acquirer, such as IBM, HP, Dell, or able to lease the /dpmaci/centida.html 330 IT execs surveyed, 53% plan to acceler- Cisco, for several months. company’s software (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) ate Linux adoption on the server this year AITP Washington D.C. at a discount of up to directly due to the economy. Additionally, April 9, 6:30 p.m. 26%. According to MicrosoftIncentives.com, 73% are “either actively evaluating or have Alfio’s Restaurant enterprises will be able to sign up to sub- 4515 Willard Ave. already decided to increase their adoption of scribe to Microsoft Office 2007, Windows Chevy Chase, Md. Linux” on the server in 2009, while 68% plan Vista, or two bundles of CALs (client access aitpwashdc.ning.com adoption on the desktop. The survey reports licenses) for server software at a significant (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) that the Americas have felt the economy’s ISSA Northeast Ohio price reduction—more than a quarter off the influence the most, with 62% already making April 9, 8 a.m. list price. The Web site says enterprises can Corporate College East budget cuts or investigating where cuts are take advantage of discounted prices when 4400 Richmond Road possible, 66% evaluating or increasing Linux they sign up for SQL Server, SharePoint, and Warrensville Heights, Ohio adoption on the desktop, and 67% doing the neoissa.org same on the server. The retail industry (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) WATCH THE showed the most potential for accelerating AITP Northeastern Wisconsin Chapter This information provides a quick glimpse of current and historical stock April 15, 4:15 p.m. STOCKS Linux adoption, with 63% planning to in- prices and trends for 14 major companies in the technology market. Holiday Inn Select crease Linux desktop adoption and 69% 150 S. Nicolet Road Linux server adoption. About 50% of respon- Appleton, Wis. dents reported that migrating to virtualization new.aitp.org % change from Company Symbol Year Ago March 5 $ March 19 $ previous issue software is speeding up Linux adoption, and (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) ISSA Oklahoma City AMD AMD $6.15 $2.16 $2.96 ▲37.04% 88% plan to evaluate, deploy, or increase vir- April 15 Computer Associates CA $22.08 $15.40 $16.60 ▲7.79% tualization software use within Linux OSes in Spaghetti Warehouse Cisco Systems CSCO $24.47 $14.55 $16.23 ▲11.55% the next two years. 101 E. Sheridan Ave. Dell DELL $19.51 $8.39 $10.04 ▲19.67% ❙ Oklahoma City, Okla. Dell Lays Off Hundreds More www.issa-okc.org Google GOOG $432 $305.64 $329.94 ▲7.95% (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) HP HPQ $46.59 $27.08 $29.10 ▲7.46% Dell further cut its forces this month, with AITP Omaha IBM IBM $116.94 $87.48 $92.66 ▲5.92% layoffs in its Texas, Tennessee, and North April 16, 5:30 p.m. Intel INTC $21.09 $12.31 $15.15 ▲23.07% Carolina factories estimated in the hundreds. Seraph Corp. The computer maker declined to officially Omaha, Neb. McAfee MFE $33.28 $28.99 $31.52 ▲8.73% confirm how many employees were affected. www.aitpomaha.org Microsoft MSFT $28.62 $15.27 $17.14 ▲12.25% The news follows Dell’s December announce- (cid:127) (cid:127) (cid:127) (cid:127) (cid:127) Oracle ORCL $19.56 $14.53 $17.37 ▲19.55% AITP Tarheel ment of plans for global reorganization and Red Hat Software RHT $16.82 $13.69 $15.65 ▲14.32% April 16, 6 p.m. the January layoff of 1,900 employees in Sun Microsystems JAVA $15.67 $4.19 $8.63 ▲105.97% Foothill Brewery Limerick, Ireland. The reductions are part of 638 W. 4th St. Symantec SYMC $16.49 $13.12 $14.18 ▲8.08% Dell’s effort to save $4 billion in annual costs Winston-Salem, N.C. www.aitp.org NOTE: This information is meant for reference only and should not be used as a basis for buy/sell decisions. by February 2011. The enterprise says it March 27, 2009 Processor.com Page 3 News Also In This Issue... TECH & TRENDS saved $1.4 billion in the last fiscal year, for comprehensive U.S. privacy legislation, helped by an 11% workforce cut, or the loss instead shifting its focus to developing the ■Deploying wireless networkscan free employees of about 9,300 jobs. Dell expects to see sav- framework that would make new governance from the creativity-crushing sameness of a hard-wired ings from restructuring its supply chain and possible. The Microsoft-led group was de- desktop computer in a hard-wired cubicle. But cutting the manufacturing network in the near future, signed to bring together a mixture of consumer cord opens up a range of security issues that network although further layoffs are expected. companies, tech companies, and advocacy administrators can’t afford to ignore....................page 34 ❙ groups to push for privacy legislation. Rather EMC Looking For Acquisitions ■Being penny-wise and pound-foolish, especially when than focusing its attention on privacy legisla- it comes to data integrity and security, can have disas- Network-storage and data-recovery company tion, the group now touts itself as “an organiza- trous consequences............................................page 35 EMC announced that it is looking for potential tion focused on fostering innovation in con- acquisitions that will help strengthen its exist- sumer privacy governance” in its new mission ■Today, many data centers use raised floorsto carry ing business. Joe Tucci, chairman, CEO, and statement. cables, electrical wiring, and cooling equipment. However, president of EMC, says the company is most ❙ ❙ more data centers are being built without them. Why is the Survey: Budget Cuts Major Threat Layoffs For Nokia interested in acquisitions that are very similar industry turning away from this concept?..............page 36 To IT Reliability to EMC, rather than venturing into new mar- Nokia is joining the ranks of other handset ■IP-enabled devicesare versatile and functional, and kets. Specifically, Tucci says acquisition tar- Budget cutbacks may cause a serious dis- manufacturers affected by the global economic they extend the advantages of an IP network to busi- gets include companies specializing in virtual ruption to data centers, according to mem- downturn with its announcement that it plans to ness functions traditionally served by analog devices. infrastructure or information infrastructure. bership surveys from AFCOM (Association lay off 1,700 employees worldwide, or about But, in doing so, they introduce risk into the network Other factors EMC is interested in are good For Computer Operations Management), an 1% of its global workforce. Nokia’s fourth- infrastructure......................................................page 37 people, obtaining new technology, and association of data center managers. Re- quarter net income dropped to $745 million accessing the new company’s customers. spondents indicate that one out of every four from $2.4 billion in the same period a year ago. TIPS & HOW TO Potential acquisitions are made possible by data centers should expect to experience a The cuts will mostly affect the Devices and EMC’s $9 billion in cash and thus its ability to disruption with their equipment in the next Markets units, the Corporate Development ■In the case of storage, hard drives have been a domi- buy companies without drawing on outside five years. In particular, respondents noted Office, and global support operations. Nokia neering inhabitant for so long that the concept of adding financing. that cuts to security would cause problems announced earlier this year that it was aiming solid-state drive technology can create unique chal- ❙ with services; for example, 6.1% are cutting to slash $910 million from its budget, even lenges when it comes to evaluation....................page 28 California Senator Wants physical security, 4.5% are scaling back data encouraging its employees to resign and ac- To Update Data Breach Law ■In an economy that favors lean operations, and with security, and 12% said that generally budget cept a severance package. data centers employing more virtualization than ever, IT California Sen. Joe Simitian is looking to cuts would cause disruptions. Of managers are increasingly facing the question of what to expand a data breach notification law that was the 133 respondents, half said that do with machines ready for retirement................page 28 introduced six years ago with a new bill called cutbacks were planned in the near SB 20. The bill would require companies to future. ■No matter how grim a current environment might look, report data breaches not only to customers, but ❙ smart enterprises never stopanticipating growth. In fact, Intel, AMD Tangle Over also to the state’s attorney general. Simitian’s at a time when many enterprises are hunkering down and Global Foundries Spinoff hope is that by reporting data breaches to a waiting for the economic storm to pass, the opportunity to central authority, California residents and offi- Intel claims that AMD violated pause and plan should be welcome......................page 30 cials would get “a better understanding of the a confidential part of a 2001 ■Properly evaluating Microsoft Windows 7 and plan- nature and scope of the problem.” According to cross-patent licensing agreement ning for its deployment is key to building a solid business Fred Cate, a law professor at Indiana Univer- between the two companies when it ❙ HP Revamps Pricing & Services case and reaping the benefits of a modern, well-man- sity, only one in 10 data breaches are made announced plans to spin off its manufacturing aged desktop......................................................page 30 public, and overall, there is very little data assets into Global Foundries, a joint venture Computer maker HP is now offering unbundled about data breaches. with the Abu Dhabi government. Intel threat- services, as well as tiered pricing in a new COMPANIES ❙ ened to revoke AMD’s x86 licenses and approach offered via EDS. Customers will be Microsoft Receives Bundling Reprieve rights, saying the latter wrongly tried to able to personalize their orders for high- and ■Storage Media Brokers provides recycled tape Microsoft has until April 21 to respond transfer Intel’s intellectual property to a third low-priority applications. Although EDS and HP cartridges and to allegations that it unfairly stifles competi- party, but AMD has countered that the legal have traditionally negotiated with major enter- other tape media tion by bundling its Internet Explorer search threat means that Intel itself has violated the prises for outsourcing, smaller clients can now to companies of engine with the company’s Windows soft- agreement. take advantage of scaled-down management all sizes................ ware, according to the European Commis- ❙ offerings for as little as 85 servers and 1,000 ................page 39 Survey: Surfers Aware sion, the European Union’s antitrust agency. service-desk seats. New managed services Of Behavioral Tracking ■Information Support Concepts provides hardware This is an extension from the original date of include server and storage operations, flexible and furnituresolutions designed for use in a variety of March 12, eight weeks after charges were About two-thirds of Internet users 18 and older computing, and managed messaging for secu- environments.................................................................... first leveled against Microsoft. The charges are aware that advertisers employ behavioral rity and compliance. HP will also provide multi- ............................................................................page 39 stem from a complaint from Opera Software tracking, says a TRUSTe survey, but users ple reliability levels, reducing overall building ASA in 2007. Since then, Mozilla and Google also seem to be growing more tolerant of the costs by 25%. ■Rather than tape-based backups, Accordance have joined in the case as “interested third practice. Only 51% of users surveyed object to ❙ Systems approaches hard drive failure preventionin a FTC Questions Cloud Computing, parties.” If it loses, Microsoft would have to third-party marketing surveillance, compared to different way: with RAID.....................................page 42 Google Services offer other browsers with Windows. 59% last year. Still, 48% of users delete brows- ❙ er cookies at least once a week in an effort The Federal Trade Commission met this PRODUCTS Digital Signage To Grow In 2009 toward better privacy, compared to 42% in month to discuss jurisdiction over potentially ■Snake Tray features A report from ABI Research estimates that 2008; however, 39% admit that they don’t ade- deceptive practices for cloud computing ser- a full line of affordable, the U.S. digital signage market will grow by quately protect their personal information on vices. On the same day the FTC convened, efficient hand-bendable about 33% this year. According to ABI Ana- the Web, even though three out of four claim to EPIC (Electronic Privacy Information Center) cable management lyst Zippy Aima, “Traditional advertising know how. filed a complaint with the commission, re- systemsand unique media are losing their appeal for many con- ❙ questing a security investigation of multiple Microsoft To Release Win7 Toolkit power distribution and sumers. Consequently, digital signage has Google cloud computing applications, such air management products...................................page 20 emerged as a way to deliver highly cus- Microsoft plans to release a toolkit next month as Google Desktop, Google Docs, and tomized and targeted messaging in a variety that will help business users test their existing Google Calendar. Although Google claims ■IT WatchDogs’ WeatherGoose line of environmen- of locations.” ABI Research’s report indicates applications for compatibility with Windows 7. that its storage is secure, EPIC disclosed tal monitorskeeps an eye on a data center’s environ- that government, law enforcement, education, This is the first time Microsoft has released the numerous privacy-related incidents in its ment, watching for abnormalities in temperature, and hospitality venues were some of the most toolkit before the general release of its new complaint. EPIC has also asked the FTC to humidity, and more...........................................page 21 likely new places to adopt digital signage. OS—Vista’s toolkit was released at the same bar Google’s cloud computing services until Technological improvements in digital sign- time—and by doing so, it will give its customers security measures are in place and Google age, such as display appearance quality and more time to test for compatibility. Those who agrees to contribute $5 million to privacy affordable data storage, also contribute to its have already tested software with Vista will research. rise in popularity. have a smooth transition, as applications that ❙ Hitachi Splits In Two run on Vista will be compatible with Windows 7. ■When an organization hits the ceiling of its network The company will release another Tokyo-based Hitachi has divided its company bandwidth, what are the alternatives? One health indus- version of the toolkit with the com- into two separate entities and named a new try real estate company turned to the Expand Networks mercial release of Windows 7, president. Beginning July 1, the company will WAN Accelerator to free up bandwidth ..............page 22 which is slated for late this year or be split into two groups; the Automotive Sys- early next year. tems Group will spin off and relocate to its own ■The Napa County Office of Education needed an ❙ headquarters with a work force of about 7,600 effective solution for archiving email safely, despite not Industry Group employees, and the Consumer Business Group having specific rules and regulations to follow. It found Changes Focus will have about 750 employees and will focus the perfect solution in Sonasoft’s SonaSafe for Email The Business Forum for Consumer on manufacturing and selling flat-panel moni- Archiving.............................................................page 22 Privacy, formerly known as the tors for consumer and commercial LCD projec- Consumer Privacy Legislative tors. Takashi Kawamura will now serve as The Processor.com home page is frequently updated with forum, has pulled back from rallying chairman, president, and CEO. new articles and hardware news to help you keep current. Visit www.processor.com today. Page 4 Processor.com March 27, 2009 P r o d u c t S h o w c a s e c o n t a c t Baytech (800) 523-2702 Low-Cost Solutions www.baytech.net To Remote Site Management & Data Center Power Baytech Devices Provide Green Solutions To Save Businesses Some Green EVERY DATA CENTER has the same core issues to managers identify and address IT issues at remote consider, including power, cooling, and the cost of locations to the ATS switch that provides power- operation. All are fundamental to successful data circuit-level redundancy to maintain uptime to a center operation. There are many ways to optimize series of outlet metering and control products. power and cooling, and cost savings can come And because Baytech’s products are designed to from a variety of areas. But in order to maximize save operational costs in part by optimizing performance and savings, data center managers power, they’re a green way to save money. need information about (or from) their devices. With remote management capabilities, safe Baytech’s line of power and remote manage- power switching for single-corded devices, and ment products addresses these needs. Baytech’s varying levels of outlet and circuit breaker con- solutions are designed to scale easily, optimize trol and monitoring, Baytech offers lines of prod- data center equipment performance, save money, ucts that are smartly designed, inexpensive, and and cover a range of needs, from the DS-RPC can save companies a great deal of money while Remote Site Management series that lets optimizing data centers for maximum efficiency. DS-RPC Remote Site Automatic Transfer Management Series Switch (ATS) MAINTAINING UPTIME is crucial to every data center and remote branch. Having redundancy on the power circuit level is a critical part of it. Baytech’s ATS device is designed to provide a simple yet reliable solution for automatically sensing power loss and seamlessly switching to a backup cir- cuit. The ATS device is designed specifically for single- corded devices, which are likely found in even the most up- to-date data center. AC signals should technically be the same voltage, but they’re often out of phase because the actual voltage differs depending upon where on the panel the feeds are pulling their power. Depending on the degree of difference, there is a great deal of energy potential between the two sides, which could seriously damage equipment. Some switches will detect the lost power and immediately switch to the other side; however, a lot of energy remains in the power supply, which could still produce a damaging spark. The ATS line of transfer switches solves this problem by actually breaking the connection to let the energy dissipate. The sine waves are reduced to zero, effectively killing any power potential, and only then will the ATS device MANY COMPANIES have remote locations that fix many of them remotely, saving the cost of a switch over. No matter how out of phase the sources may be, the ATS device need onsite data applications, such as banks and repair visit and reducing downtime. can safely make the switch. retail stores. When a problem arises at those Of course, in some cases, the repair cannot be The switching time, even with the break, is between 8 and 15ms—about the sites, usually a repair person must be deployed to done remotely, as in the case of a failed device. length of one 60Hz AC cycle—so performance is not affected. discover and subsequently fix the problem. One However, because the DS-RPC devices can rule The ATS devices also provide monitoring, so data center managers can complication that sometimes arises is that the out a number of issues ahead of time, the repair glean information about amperage load, true RMS power (watts), volt-amps, repair person discovers that fixing the problem person will know what’s in store for him. For voltage, and internal temperature. When combined with a DS series device’s will require additional equipment that they don’t example, if the problem is identified as a device console server, alerts on power and transfers can be sent via secure SNMP v3. have with them. Thus, they have to leave, acquire failure, he could arrive onsite with the necessary Other standard features of the ATS devices include programmable dropout the proper equipment, and come back a second part in hand. voltage, programmable switchback voltage, SNMP and HTTP (with a DS time to replace the faulty equipment. Features of the DS-RPC series include console series device), and PCB-based reliability. In addition to the cost of two site visits by a port management, device port naming, individual repair person, the organization will lose money port password assignment, direct TCP port because of the downtime created by the initial access, and Telnet/SSH menu device selection. problem and the time it takes for someone to Users also have remote and HTTP power control make two visits and fix whatever is amiss. and true RMS voltage and current information. The BayTech DS-RPC remote site manage- Security features include SSH v2, RADIUS ment series of products provides secure and reli- authentication, and SNMP and user account lists able management for the network, servers, and per port to allow system administrators to console ports. The DS-RPC remote site manage- remotely manage the DS series with greater con- ment devices let you both identify a problem and fidence and control. March 27, 2009 Processor.com Page 5 P r o d u c t S h o w c a s e MRP (Modular Rack Power) MRP Metered Metered Power Strip & Controlled Outlets MUCH MORE THAN a simple strip of outlets for data center Having the metrics on not only the circuit breaker on the hardware, Baytech’s line of metered outlets is designed to panel, but also the circuit breaker on the power strip enables give data center managers critical information about the you to make intelligent decisions when deciding to purchase efficiency of the devices attached to the power strip. servers. When considering a purchase, users need to exam- BAYTECH OFFERS a line of metered outlet products that Many products give you information only on the circuit ine issues of performance, function, and capability, but they gives you the features of metered outlets with the power- breakers on the panel. Baytech’s metered power strips also also need data on how efficient a particular server is. In ful addition of outlet control. Having actual control over provide metrics on the circuit breaker on the power strip other words, they want to know how much power a device the outlets is a powerful way to integrate remote man- itself. The metered outlet modules offer reports on amps, uses in comparison to how much processing power it has. agement into data center monitoring. For example, if a voltage, voltage-amps, watts, power factor, and efficiency Other features of the metered outlet modules include sup- piece of equipment is locked up, it may simply need to per receptacle. As a result, the information from the metered port for 20, 30, 50, or 60 amps; on, off, and reboot options; be rebooted. Because you have control, you can reboot strips will help data center managers avoid tripping breakers HTTP, SSH, and SSL access; RADIUS and TACACS the device remotely. and damaging entire racks of equipment. authentication; and tool-less mounting. Reports include Another issue commonly faced is the problem of not All of this data helps data center managers discover other information on power factor per outlet, kW hour per outlet, having enough power available for every receptacle in issues. For example, the module may report that a given current, voltage, volt-amps, and watts. All metered outlets a strip. With outlet control, data center managers can device is pulling 12kW, while the cooling solution for that feature a modular design for optimum scalability, as well as turn off those unused outlets. This ability translates area is configured for only 8kW. Thus, you can discover a PCB power distribution and fail functional design. into potentially large savings in energy costs. A device hot spot in the data center. All of Baytech’s MRP devices are designed to securely that is connected to a power source, even if it’s turned Another problem that the metered outlets help solve is hold devices in the receptacles and for extraordinary dura- off, is still drawing quite a bit of power, which means predicting when a given device is about to fail. Before hard- bility. With high retention and locking receptacles, MRP simply turning off a server doesn’t result in as much ware fails, it usually becomes less efficient. The metered devices are designed to hold any and every connected power savings as if the outlet were also off. Baytech’s outlets will provide data showing a reduction in a device’s device, even if the weight of the cable is pulling on them. In metered outlet module with outlet control lets users efficiency long before it fails, giving data center managers addition, Baytech uses PCB-mounted receptacles, so there turn off both the device and the outlet, resulting in sig- weeks or months of notice before a device fails. are no cold-soldered connections in the MRP devices. nificant energy savings. All Circuit Breakers Monitored Outlet Metering With Efficiency Locking C13 Receptacle Optional Reliable PCB Power Distribution Integrated Sensor Inputs Most metered power solutions only Monitor individual outlets and receive Reliable integrated locking clips ISD (Insulation Displacement) con- Eliminate the need for extra environmen- monitor input power. BayTech moni- current, watts, and volt-amps. assure power cord retention. Unique nectors are faulty and unreliable! All tal monitoring devices. All BayTech tors all circuit breakers and reports Continuously monitoring equipment to the industry and does away with BayTech power solutions use reli- power solutions offer two ports for exter- via SNMP when thresholds are met. for efficiency with power factor. nuisance wire clips. able PCB power distribution. nal temperature and humidity probes. Controller Module Receptacle Module MRP Metered MRP Metered Power Power Strip With Strip & Circuit Metering Outlet Control & Without Outlet Control Circuit Metering NOT EVERY DATA CENTER needs outlet low-density models and support 120 control, but you might still want the valu- /208/AC single-phase and 208/400VAC able information provided by the metering three-phase and include the standard fea- IN ADDITION TO providing products that offer metering at the circuit-breaker level and con- of outlets and circuit breakers. For those tures of the other MRP device types. trol at the outlet level, Baytech also has a line of devices that meters at the outlet level. With customers, Baytech offers devices without Unique features include monitoring of these devices, users can glean a power factor for each device plugged into a cabinet in addi- outlet monitoring. all circuit breakers; a kW hour meter; tion to the cabinet itself. Like the metered strips with both cir- meters for current, voltage, and watts; These devices give you a tool to drill down to find the most inefficient server, which you cuit metering and outlet control, these and an optional integrated interlocking can use to determine what hardware needs to be replaced to maximize data center efficiency. devices are available in both high- and C13 receptacle. Page 6 Processor.com March 27, 2009 Cut HVAC Power Usage with little change to the heat load, which Top Tip: Fix Your Floor positively impacts your power usage.” Make The Utility Bill Visible Continued from Page 1 Digital Fortress (www.digitalfortress.ca). According to Tim Hirschenhofer, director of managing airflow—possibly through airflow “You’ll be the first one to fry.” It may be difficult to appreciate exces- sales for Degree Controls’ AdaptivCool divi- management units under a raised floor or in Spencer adds that drive arrays should be sive energy consumption as long as some- sion (www.adaptivcool.com), leaky raised a dropped ceiling—you eliminate hot spots. moved toward the floor, as they’re heavier one else is paying the bill. floors allow cold and warm air to mix, which “You’re not adding more cooling. Rather, and tend to run hotter. Adjusting vertical “A lot of folks are being shown that elec- forces CRACs to work harder and suck up you’re using what you’ve got more effec- placement reduces hot spots and improves tric bill now, and they’re being held account- more power. Seal off open cable cutouts and tively,” Hirschenhofer says. “This allows cooling efficiency. able,” says Kubik. “So whether there’s a use blanking panels to actively manage air- you to run your cooling equipment much UPSes can also be major sources of wast- problem or not, they’ll have to run through flow down low. Train data center employees more efficiently so you don’t have to cool to ed energy. Kubik says a UPS with a low the paces to see what they can do to reduce to manage floor tiles appropriately and avoid the warmest spot in the room anymore.” power load is significantly less efficient power consumption.” leaving unnecessary openings following Additionally, anything that blocks the than one running closer to its load capacity. This level of visibility makes it easier to equipment moves, additions, and changes. free flow of air above or below a raised He recommends consolidating them to raise track energy performance in the data center. floor raises the potential for hot spots. efficiency. As an added bonus, consolida- “Many shops don’t measure their consump- “The room doesn’t have to feel like a “Servers should ideally be pulling cold tion simplifies management. tion as diligently as they could be,” says meat locker to adequately cool the equip- air from the front and exhausting warm air Kubik. “So it’s been a free-for-all—they add ment,” says Hirschenhofer. “It’s okay for Accelerate Virtualization out the back,” says Rob Kubik, power and a UPS here, a cooling unit there, all to server intake temperatures to go as high as cooling specialist at CDW. “A badly placed Today’s multicore processor-based serv- address tactical cooling needs. But they don’t 77 degrees and still be in the safe zone. power strip, UPS, or cable can get in the ers run more processes and applications really know what they’re consuming.” That’s a little bit hard for some data man- way. Sometimes, even a simple adjustment more efficiently, delivering greater capacity agers to accept. They’d much rather walk Change Your Thinking can allow the air to go in and out as quickly without commensurate increases in heat into the room and be cold immediately.” as possible.” loads or energy consumption. Saving energy in the data center is as Additionally, Kubik says there’s often a “Virtualization makes more processor much based on attitude adjustment as it is disconnect between IT and facilities. “Even Maintain Your Equipment & Its Placement cycles available for less heat load,” says on changes to physical infrastructure. though their offices may be across the hall Equipment placement within a rack is Spencer. “It also scales extremely well, Changes to long-held assumptions about from each other, they’re not necessarily crucial to effective cooling, airflow, and allowing you to, for example, go from 1,000 environmental management can go a long talking,” he says. “We encourage everybody energy conservation. In a partially empty to 2,000 concurrent users on the same box way toward driving efficiencies. to get onto the same page.” rack, move the installed devices as close to As an example, airflow management ini- the floor as possible to take advantage of tiatives that move hot air into a drop ceiling the cooler air below. Bottom-to-top place- “The room doesn’t have to feel like a meat may cause ripple effects beyond the data ment also gives you more redundancy in center. If the building uses the plenum space locker to adequately cool the equipment.” the event of an outage. for other systems, hot air from the data cen- “Being at the top of the rack is not the ter may cause problems there. Stronger part- place to be if there’s a cooling failure,” -Degree Controls’ Tim Hirschenhofer nerships can ensure win-win solutions for says Steve Spencer, president and CTO of both IT and the facilities teams. P Are Flywheels For You? counterparts, but Active Power’s Rackow Going green can pay dividends in other states that flywheel solutions can recoup ways. Active Power’s Rackow notes one their higher costs in 18 to 24 months. This user who installed about 2 megawatts of Continued from Page 1 Viewed from a thermal angle, the bat- ROI hinges on several less-discussed liabil- flywheel UPS product. The customer then of sales for the Americas at Active Power tery proposition is even more erroneous. ities with battery technology. Battery life- went to the local power company, (www.activepower.com), this battery run- As Pentadyne (www.pentadyne.com) lit- times are generally rated with a 100% fig- explained that they opted for the more time is his company’s chief competition. erature illustrates, today’s servers and ure dependent on the battery never being power-efficient flywheel solution over Rackow notes that years ago, it was com- rack densities have rigid environmental used. Every instance of battery usage conventional battery, and the utility cut mon for mainframes to run single applica- cooling demands. If the power fails, “you lessens its potential maximum utility, and the company a rebate check for $125,000. tions. He used to watch IBM practice have less than 60 seconds to have the load sags and cuts occur regularly to busi- Rackow says that many power companies drills in which an application went genset online and powering the cooling nesses. Some record hundreds of such offer such programs, as it defers the through an orderly shutdown in less than systems; otherwise thermal server crash is drops per year. Moreover, batteries must be expenses they would incur in building out 10 minutes, and so a 10-minute UPS was inevitable.” maintained at under 75 degrees Fahrenheit more infrastructure, but few data center perfect. Today, though, with data centers managers know of or claim these Flywheel Rationale running multiple applications across mul- rebates. tiple systems, such numbers are impracti- There are three reasons to consid- “There’s a lot of concern now cal. The race is not to shut down the appli- er a flywheel-based UPS solution: about energy efficiency and the cations; it’s to power up the generators. If space, long-term cost, and environ- greenness of your company,” says the generator doesn’t start, Rackow mental concerns. Space is the sim- Forrester’s Staten. “Having lead asserts, people who think one can be plest. Active Power’s Rackow acid or even lithium ion batteries repaired in less than 10 or 15 minutes are draws the picture of a flywheel- exposes you to hazardous waste deluding themselves. based UPS occupying a 4-foot disposal expenses. If you’re in “Properly designed engine systems are square closet while an equivalent Europe, where carbon credits are a typically running and under load in eight battery-based UPS occupies the concern and hazardous waste can seconds,” he says. “The national electric same depth but is 20 feet long. be a rather expensive thing to deal code for all health care facilities requires Magnified across the expanse of a with, this is far more appealing. that their standby engines must be started in data center and its many systems, But now that there’s a lot of U.S. under 10 seconds. Everybody’s had an that’s a lot of dead real estate devot- companies that care about energy engine that can do that for years. If they’re ed to batteries that might otherwise efficiency, even without the car- properly maintained, it’s not an issue. You be earning revenue. bon credits, this is a more appeal- don’t need 15 minutes. You really don’t Long-term costs and environmen- ing technology than it’s been in even need 15 seconds. But for some people, tal concerns can be closely tied, as the past.” it’s a giant leap of faith to go there.” in the relationship between local Staten points out that “a fly- “Most modern generators will ignite in resources and the cost of electricity, wheel solution is also magnitudes five minutes or less,” adds Forrester ana- or polar opposites. As Forrester’s better toward getting LEED certi- Flywheel UPSes are mechanical devices that store rotational energy. lyst James Staten, who says that most Staten notes, “In a down economy, fication than battery backup.” The implementations of new flywheels give ‘green’ goes from being environ- LEED (Leadership in Energy and you more than five minutes. “There’s mental to being about money. We’re just for optimal performance, a much costlier Environmental Design) Green Building much more of a connection between the not seeing people doing anything for purely proposition when battery-based UPSes are Rating System (www.usgbc.org/leed) out- two at this point,” he continues. “You see environmental benefits. It’s all about eco- 6 to 8% less power efficient than flywheel- lines a lengthy set of standards for eco- those kind of generators a lot in tier 4 data nomic benefits.” based UPSes, according to Active Power. friendly construction. LEED-compliant centers, which have mission criticality Flywheel-based systems carry higher ini- Pentadyne pegs UPS battery MTBF at buildings may be more expensive to build, and never go down.” tial price tags than their battery-based around 10,000 hours. Its flywheel devices but many states offer significant tax incen- are rated at 875,000 hours. Containment tives for adherence; plus, there are less tan- requirements for battery systems exist gible public perception benefits tied to Flywheel-based systems carry higher because batteries can swell and split, being LEED-certified. releasing toxic chemicals and gases. True enough, larger data centers will initial price tags than their battery-based Battery states in general are difficult to recoup the added expense of buying a fly- gauge and time-intensive to maintain, and wheel-based UPS solution more quickly counterparts, but Active Power’s many data centers don’t maintain batter- than an SME. But the more a data center ies as well as they should. Poor battery planner cares about environmental con- Gary Rackow says flywheel solutions can maintenance can lead to literally explo- cerns and is willing to take a longer-term sive results. In comparison, flywheel tech- view on ROI, the more flywheel technolo- recoup their higher costs in 18 to 24 months. nology entails nearly no maintenance time gy will become a persuasive proposition, or expense. especially for new data center builds. P March 27, 2009 Processor.com Page 7 Save Data Center Power News ❙ New Google Project Is Delayed By Updating Equipment Google has delayed plans for its Project 10- to-the-100th. The company was expected to launch ideas for the project this month but claims it underestimated the time it would take to sort through all the submissions. According to the project’s Web site, Project Power Costs Can Be Lessened For Tomorrow 10-to-the-100th is designed to gather ideas Key Points for projects that can change the world for the By Employing Fresh Buying Strategies Today better by helping people; the company plans (cid:127) Think of all aspects of the data center as to support each of the top five ideas with $10 by Elizabeth Millard a few dollars on this equipment, but it’s ripe for power-related upgrades, including million in funding. The public will vote to nar- (cid:127) (cid:127) (cid:127) usually better to go for the best available UPS systems, blade server components, row the list to 20 possible ideas, from which a OLDER EQUIPMENT CAN BE A DRAIN on power supplies, even if it bites into the bud- temperature monitors, and air conditioners. committee will select the top five. power sources because it can lack the effi- get, says Jack Pouchet, director of energy (cid:127) Upgrade cabinets, as well as servers. ❙ Cybersquatting On The Rise ciency of newer machines. Not only do initiatives at Emerson Network Power (cid:127) Consider refurbished equipment for a older systems take more electricity, but (www.emerson.com). WIPO (World Intellectual Property Organi- green touch to the data center. they might also need more cooling, which Look for power supply systems that zation) reported a sharp rise in the number creates another source of power loss. It deliver about 90% efficiency, he advises, (cid:127) Virtualize before upgrading to reduce the of cybersquatting cases—reports of individ- makes sense, then, that updating equipment rather than paying less for the systems that number of servers needed. uals or organizations registering a well- can mean saving power in the long run. promise about 75% efficiency. That small known brand or company name as an boost in efficiency will be important for they’re concerned about response time, he Internet domain name in order to illegally Update Every Type Of Equipment long-range power savings. adds, but those built-in controls are often profit—filed by trademark holders. The Although servers tend to be a strong Also important are management systems intelligent enough at switching to keep any record 2,329 complaints mark an increase focus for buying, power bills can often that can create more automation, Pouchet response-time issues to a minimum. of 8% year-over-year. MarkMonitor, another be driven up by inadequate copyright protection service, also reported Think Green cooling measures. For exam- 440,584 instances of cybersquatting in the When Upgrading ple, Franklin & Marshall Col- fourth quarter of 2008, 18% more than in lege in Lancaster, Pa., had The greening of the data 2007. Increases in cybersquatting have in place two air conditioners center remains a hot topic; made trademark holders leery of ICANN’s that were both 25 years old. subsequently, there are plenty (Internet Corporation for Assigned Names The amount of cooling they of manufacturers offering and Numbers’) proposed plan to open cus- pushed out turned the data equipment that promises to tom top-level domains, allowing for domains center so cold that it was like run at a higher level of effi- such as .coke or .google. ICANN has re- walking into a refrigerator, ciency than in the past. cently decided to delay its plans until it notes Josh Baron, the col- To create a greener tinge to investigates the problem further. lege’s system administrator. a data center, talk to manufac- ❙ More Satyam Customers The college replaced the turers about what kind of Consider Exits units with a single air condi- power savings could be real- tioner that also had humidity ized by switching to their Clients of outsourcer Satyam Computer controls, and there was an products, but also consider Services continue to leave the fraud-strick- instant boost in efficiency. refurbished equipment for en company despite its attempts to restore Also, because the unit could upgrade needs. Particularly channel the air more intelli- at remote offices or with gently, the general tempera- lower storage tiers, this type ture of the room didn’t have to of equipment can be helpful be so icy. (For more informa- with virtualization strategies tion on saving power through (see the “Top Tip: Virtualize” cooling, see “Cut HVAC Pow- sidebar for more information) er Usage” on page XX.) and can fall in line with larger Also ideal for updating are company goals toward greener monitors and other controls. operations. Data centers often rely on temperature notes. He points out that data centers are Find Efficiency At The Cabinet Level monitors to keep power and cooling on often sized for peak conditions but that track, but these smaller pieces of equip- those conditions rarely exist, creating a Because so many cabinets and racks ment can experience wear and tear just power consumption level that remains high now have cooling and power-monitoring like servers or cooling systems. Talk to even when the server load is low. capabilities, they can be as important in manufacturers about expected life span of “Some IT managers disable the built-in an upgrade plan as servers and other these types of controls and make sure power management features that are part of equipment. there’s a plan in place to revamp them before that end date so that monitoring internal stability and bring in a strategic “Some IT managers disable the built-in tactics stay fresh. partner to see it through its financial crisis. Even the individual parts of blade servers Former Satyam Chairman Ramalinga Raju power management features that are part can be considered for upgrades. According admitted in January to falsifying more than to a recent whitepaper from Emerson Net- of server processors, but they may want $1 billion in assets while overstating quar- work Power, it can boost energy efficiency terly earnings and revenue by up to 28%, to upgrade specific components within a to reconsider that strategy.” causing a 75% drop in the company’s stock. blade system, such as power supplies, mem- So far, more than 40 clients have left or are ory modules, processors, and fans. planning to leave Satyam, including IBM, - Emerson Network Power’s Jack Pouchet State Farm Insurance, Citigroup, Merrill Spiff Up Your UPS Systems Lynch, GlaxoSmithKline, and Coca-Cola. & Management Systems server processors, but they may want to It may be worth the investment to get Nissan and Pfizer are also believed to be With low-cost UPS options available in reconsider that strategy,” he says. The man- customized cabinets that are suited to a spe- considering other options. the marketplace, it can be tempting to save agers often employ this tactic because cific space, says Steve Prather, senior vice ❙ Report: Printer Market Struggling president of sales engineering and opera- tions for ViaWest (www.viawest.net), a According to a new Gartner report, the print- Top Tip: Virtualize colocation and managed services provider. er, copier, and multifunction device market He notes that some data centers are in older reported a 5.9% drop in the number of ship- Many data centers have been finding that for more efficiency is crucial, says Larry buildings that could have limitations in ments for 2008, compared with 2.9% growth instead of replacing servers, it makes more Owens, the college’s system manager. The terms of air exhaust and heat return areas. in 2007. Analysts also don’t expect the mar- sense to use virtualization applications to college has been using virtualization to re- There may also be considerations in ket to recover until well into 2010. Gartner reduce the number of servers needed. The duce server numbers and began by targeting bringing fresh air into the system or work- blames companies opting to hold off on major strategy cuts down on purchasing, and be- larger servers. ing with existing power consumption purchases and extending the typical three- cause there are fewer machines, there are issues. Not all the cabinetry has to be cus- year replacement cycle as key reasons for also significant savings in power consumption. “It’s a transitional thing, to get rid of those physi- tom-built, but it could be advantageous to the continued decline. It’s not all doom and cal servers and not use as much equipment,” work with a data center designer or archi- gloom for printers, though; Gartner reports For instance, at Franklin & Marshall College Owens says. “The result is that we save on tect that specializes in data center projects. that shipments of color page copiers/MFPs in Lancaster, Pa., there are two people on hardware [and] centralize storage, and there’s These experts can lend insight into what increased 13.2% in Q4, which marks the third staff to handle about 100 servers, so the need no power waste.” needs to be upgraded, particularly with the consecutive quarter of growth. goal of power consumption savings. P Page 8 Processor.com March 27, 2009 Scale Back News Key Points (cid:127) Reorganizing your stored data can free up IT Spending space or even allow you to shut off entire A Mixed Bag For 2009 Storage Power drives or servers. (cid:127) Hosted service providers can offset the costs associated with increasing data As the economy struggles to reignite the stores by handling the power and cooling engine of growth in 2009, those responsible for you. for IT budgets are planning to make some spending adjustments in the months ahead. Shuffling Your Data Or Moving To The Cloud (cid:127) Compressing stored data can reduce the amount of storage needed and increase Can Help Decrease Power Consumed By Storage London-based Datamonitor surveyed IT storage performance. managers, CIOs, and IT decision makers in the United States, UK, Spain, Australia, by George Crump not there because it has to be retained or [is France, Germany, Italy, Benelux (Belgium, Consider The Cloud (cid:127) (cid:127) (cid:127) needed] to meet a legal compliance; most THERE ARE TWO KEY POWER CONSUMERS of it is there because no one has taken Another power-saving option, albeit one when it comes to storage: the physical the time to delete it, or it is there ‘just in that requires a small outlay in expense, is to drives themselves and the shelves that case,’” says Tony Cerqueira, president of move your archived data to a cloud storage they go in. According to a 2008 IDC report, Cofio Software (www.cofio.com). service. Cloud storage lets an SME lever- the total cost to power and cool a drive is This data needs to be understood and age the Internet to transport certain types about 48 watts per drive: 12 watts are con- managed. Data retention policies should be of data—for example, archived data—to sumed by each hard drive, 12 watts are created and adhered to, and the stored another data center whose sole purpose is consumed by the storage shelf to manage storage. (HBA, fans, power supply), “By storing data with a cloud and an additional 24 watts are storage provider, overall power required to cool the hard drives consumptionfor data storageis and the storage shelf. When minimized,” says Moe Ker- you consider that most storage mani, CEO and president of shelves hold at least 12 drives, Bycast (www.bycast.com). it’s easy to see that SMEs must “The provider reduces power work hard to control storage usageby consolidatingdata and power use. optimizing its storage across Focusing on storage power multiple customers while efficiency is environmentally making the most power-effi- friendly and helps you save cient choices possible for its the Netherlands, Luxembourg), and Nor- money, which is a key theme centralized storage system. The dics (Denmark, Finland, Iceland, Norway, for every area of the data center end user reduces power con- Sweden) to determine how IT budgets will in today’s economic climate. sumption and capital costs by fare in each country in the coming year. Here are some specific steps not having to maintain or grow About 8% of those surveyed say they plan and inexpensive add-ons you infrastructure for storage, pow- to significantly decrease their IT budget in can implement in your storage er,and coolingon premise.” 2009, which is up from just 3% of those environment to help reduce Moving to the cloud may surveyed six months prior. The group your power consumption. concern some customers that planning to slightly decrease budgets also have high-risk data governed grew from 8% to 12% between the first Reorganize Data by legal compliance guide- and second half of 2008. The percentage “The first step is to reorga- lines, but many service pro- that plans to keep the IT budgets flat was nize your data,” says Steve viders are able to maintain up to 54% compared to 51% from six Harding, director of marketing those standards. At a mini- months ago. About 20% of the respondents for Dallas-based Tek-Tools (www.tek- information should be managed either man- mum, cloud storage is an ideal way to store say they plan some kind of IT spending tools.com). “Most customers have far more ually or through software that clears off old old data that does not need to be legally cuts, but 26% plan to spend more on IT capacity than they actually need, and by data. “Only data that needs to be retained retained but is not ready for deletion. (19% plan to spend slightly more; 7% sig- creating smaller array groups that have less for a legal compliance reason or that will nificantly more). Compress Your Storage assigned capacity, a customer could reorga- have value in future research should be Companies Most Impacted nize data so that [fewer] shelves of storage maintained,” says Cerqueira. “Regardless, An option that can complement or be used in place of data reorganization is to Daniel Okubo, technology analyst at Data- compress active storage. “Using real-time monitor, says, “Our most interesting finding “By creating smaller array groups that have compression appliances, storage adminis- was that when we compared our results to a trators can effectively cut the required stor- recent report conducted by the IMF (Inter- less assigned capacity, a customer could age space by at least 50%, and they can national Monetary Fund), which forecasts enhance their storage performance and uti- reorganize data so that [fewer] shelves of GDP growth, the countries they said were lization,” says Peter Smails, vice president going to be worst affected in 2009 were of worldwide marketing at Storwize (www storage would actually be needed. These the U.S., Spain, France, the UK, Italy, Ger- .storwize.com). many—the major developed economies. shelves could then be powered off until Once compressed, the data can still be Countries in which GDP growth was still reorganized as described above. Real-time positive were Australia, Benelux, and Nor- such time as they are needed again.” compression is unique in that it works dics. When we compared that survey to the not only on passive data but on active pri- survey we conducted of IT decision makers mary storage data, as well. “Unlike other - Tek-Tools’ Steve Harding in those same countries, we found that our data reduction technologies, real-time com- results correlated almost exactly.” pression addresses the problem [with] pri- would actually be needed. These shelves all of this data needs to be migrated to a mary storage [by] creating capacity, cost, But Okubo still sees growth potential. “Even could then be powered off until such time secondary storage based on sound data power, and cooling benefits throughout the in the countries [most] affected, such as as they are needed again.” retention policies.” entire data life cycle.” says Smails. P France, the UK, and Italy, there are still Turning off shelves of unused storage opportunities. . . . Vertical markets, including can be a challenging task. Most array ven- the media industry, energy and utilities, gov- Top Tip: Save Power By Doing Fewer Backups dors suggest writing data across shelves for ernment, communications, healthcare, and additional redundancy; even when trying to education, are all experiencing stable IT minimize the quantity of physical drives One of the key things administrators can do if often, and if disk is being used with tape, less spending. Worst hit were the insurance agen- consumed, there is still a need to have some they have tape libraries or are doing backups disk has to be maintained and powered cies, retail banking, financial markets, and multishelf redundancy. Therefore, the goal to disk is run fewer backups. Although this because most of the full backups can reside pharmaceuticals.” is to balance power efficiency by limiting may sound like blasphemy, the fact is that on tape.” the number of shelves without reducing many IT professionals don’t take advantage Over the next six months, Okubo expects IT availability. Although this can be done of what they have. “By leveraging disk or Tape can also be leveraged for data reorgani- spending to continue to trend downward pro- manually, storage administrators should automation, customers should be able to do zation and compression, and unlike a disk drive, portionally to that country’s GDP slump. “And consider tools that allow them to better mostly incremental backups and do [fewer] full an idle tape uses no power for maximum effi- if you follow the consensus that the economy understand what storage is where. backups,” says Bob Koecheler, senior vice ciency. Koecheler suggests that the tape library is going to get worse in 2009, then the logic Reorganizing data to turn off storage president of worldwide sales for Spectra Logic be able to utilize technology that will allow the is that IT budgets are also going to be nega- shelves is also going to require getting rid (www.spectralogic.com). “In many environ- user to know that the integrity of the tape media tively affected.” of all or much of the data on disk, so know- ments, full backups run all night, if not all is constantly monitored; that way, when a ing what this data is and why it is still weekend. . . . Doing fewer full backups means restore from the archive occurs, there is confi- by Andrew Leibman being stored is an important consideration. that the tape drives run at full power less dence that it will work. “Most of the data stored on disk today is March 27, 2009 Processor.com Page 9 Desktop News Key Points (cid:127) Powering off end points and peripherals Study Shows at the end of the day can save on Power Savings energy costs. Immigrants Returning (cid:127) Centralized power management software Home For Work can take some of the guesswork out of managing endpoint power consumption. A recent study from the Ewing Marion Kauff- (cid:127) Outfit users according to what they need, man Foundation found that restrictions on for- Endpoint Power Consumption not what they want, to avoid overpowered, eign workers may have a negative effect on resource-hungry desktops. Could Be Costing You A Fortune America’s rising unemployment rate. Vivek Wadhwa, one of the study’s researchers, by Drew Robb in the associated power and cooling over- If power management features are acti- says, “In the past, America has been the only (cid:127) (cid:127) (cid:127) head. Although it may not seem like much, vated on all devices, though, Gartner advis- land of opportunity, and we’ve taken for grant- END POINTS ARE EVERYWHERE, from desk- an organization with 1,000 desktops may es companies not to switch off or unplug ed that the most skilled, highly talented people tops and notebooks to monitors and print- have as many as 2,000 total end points. desktops after hours because doing so may will come here. The results show that countries ers, and whether they’re actively used or That’s an annual savings of $48,000. mean that software updates and patches like India and China are offering greater oppor- not, they are sucking tons of power and “Conservatively, organizations can save can’t be performed, technicians can’t main- tunities to immigrants.” Wadhwa goes onto say costing organizations a fortune. The good 40% of desktop energy use or more,” says tain or repair machines remotely, and back- that, “when immigrants went back home, they news is there are several ways to slash the Warren Ross, global director of endpoint ups can’t be done. In organizations where saw greater job opportunity and the study power bill. product marketing at Capgemini (www these factors are not a concern and won’t respondents said they were doing much better .capgemini.com). “There is a simple step impact productivity, unplugging machines Powering Off in their careers. They felt they were moving up brings further power reduc- in the company hierarchy, had a better quality Not so long ago, a debate tions and additional cost of life, [and were] growing faster and achieving raged as to whether it was savings. more success than in America.” better to turn off equipment Right Sizing at night or leave it running. Would the loss of immigrant brain power hurt One argument was that it It’s well known that every the United States? The study states that might be better to leave the user wants the most pow- immigrant-founded, U.S.-based companies hard drives spinning than erful processor, the beefi- employed 450,000 workers and generated to have them started and est machine, and the most $52 billion in revenue in 2006. Immigrants stopped on a daily basis. RAM, but you shouldn’t founded more than a quarter of all U.S. engi- Fears about increased fail- give it to them unless their neering and technology companies started ure rates from starts and degree of productivity justi- between 1995 and 2005, including more than stops, however, are no long- fies it. The desktop electrici- half in the Silicon Valley. Additionally, the er a major issue. ty footprint can be cut down Kauffman Foundation indicates that immi- These days, the attention by right sizing of desktop grant inventors contributed to more than a has shifted to how to elimi- components. Every watt quarter of the United States’ global patent nate power waste from reduced at the CPU, for applications. those machines. Having example, saves an addition- someone go around and turn al watt or more on the fans, Study, Then Return Home off all desktops, printers, power supplies, power dis- The study surveyed 1,200 Indians and Chi- and other equipment at the tribution units, uninterrupt- nese who worked or studied in the United end of the workday or on ible power supplies, and States and then returned home. About 80% weekends can produce sig- HVAC systems. have master’s degrees or doctorates in man- nificant savings. If you are in the midst of agement, technology, or science. More than “The best way to save rolling out better processors half of those surveyed have already or plan to money with end points is to or a RAM upgrade to your start their own businesses, and only 25% say shut off the power at night, user population, for in- they are likely to return to the United States. during holidays, and on stance, put the project on weekends when the equipment would oth- which can be taken that does not require temporary hold and re-evaluate the power “It’s very likely their talents will now benefit erwise be powered on,” says Kenneth Brill, the purchase of any hardware or soft- consequences. Take the case of memory: the countries they return to. The U.S. govern- executive director of the Uptime Institute. ware. SMBs can cut power consumption Adding a little more memory might equate ment and business community must find bet- “This can reduce consumption by 30 to 75 and save money, critical for these trying to 10 more watts. Over the life of the desk- ter ways to offer good jobs and place less watts per machine.” economic times, by implementing a policy top, that unneeded 10 watts has an energy restrictive visa policies to recapture many of Take the case of a city where electricity requiring employees to shut off and pow- cost of $28 per year, according to Brill. the surveyed immigrants,” Wadhwa says. costs 8 cents per kilowatt hour. That er down their computers before leaving “Depending on type, memory consumes equates to annual energy savings per at night.” energy whether used or not,” says Brill. machine of around $24, as well as a decline “Right sizing of desktop components is a Centralized Power Shutdown good way to cut energy costs.” Depending on users to turn off their own Top Tip: Use What Utilization Inventory machines usually doesn’t work. Assigning You Already Have someone this duty is a better approach. But Another trick is to be on the alert for the most effective way is to install comput- unused equipment. Almost every office has er management or power management soft- desktops, printers, or other devices that are While it’s true that you can buy power man- ware to turn off networked devices (not just either not used at all or are used only a few agement software that can save money in PCs) when not in use. times a month. The best way to go about terms of desktop consumption, you may “Much attention on power consumption finding these unused assets is to conduct a already have the basics for such a system in has focused on the data center, but PC utilization inventory on end points. Go what you already have deployed on the desk- power consumption in an organization can from desk to desk and find out what is top or laptop. Windows Vista, for instance, also be significant, especially given steadi- there. The likelihood is that at least a cou- includes power management features that ly rising electricity prices,” says Federica ple of machines are sitting unused, gather- provide more efficient sleep states after 60 Troni, principal analyst at Gartner. “IT ing dust. minutes of idle time. organizations should recognize that the “Old equipment needs to die, so it is greatest savings come from employing smart to turn off and remove comatose “Even if someone leaves the PC powered power management features.” desktops,” says Brill. P on overnight, the system will by default go Many of the returnees cite career and quality into a sleep state after an hour to help save of life as the main reasons to return to their power,” says Warren Ross,global director of “The best way to save money with end points country. About 87% of Chinese and 79% of endpoint product marketing at Capgemini Indians surveyed say that the growing de- (www.capgemini.com).“Microsoft testing has is to shut off the power at night, during mand for their particular skill set was a key shown that the default power management factor. Family considerations are also strong settings could save businesses up to 46% in holidays, and on weekends when the motivators: 89.4% of Indians and 79.1% of power bills.” Chinese indicate that being close to family equipment would otherwise be powered on. and friends made a significant impact in the Further, the remote power-up capabilities of choice. The limited availability of H-1B visas This can reduce consumption some processors mean that even PCs in contributes to the reasons for immigrants these Vista sleep modes can now be remotely returning home for work. by 30 to 75 watts per machine.” and securely powered up as needed for up- dates and patching. by Nathan Lake - Uptime Institute’s Kenneth Brill Page 10 Processor.com March 27, 2009 PHYSICAL INFRASTRUCTURE NETWORKING & VPN Black Box ServSwitch Wizard 8-Port DVI Dual-Link (USB) is ideal for users who depend on high-resolution video performance and need the flexibility SeriousBit NetBalancer is an to use multiple peripheral devices. Internet traffic control and ServSwitch Wizard 8-Port DVI Dual-Link monitoring tool designed for (USB) (KV2008A): $1,179.95 Windows XP/2003/Vista. ServSwitch Wizard 4-Port DVI Dual-Link +373-7945-3294 (USB) (KV2004A): $449.95 www.seriousbit.com (888) 225-6921 www.blackbox.com/go/ServSwitchWizard USB True Emulation, Hotkey Support & Immediate Switching Black Box ServSwitch Wizard Internet Traffic Control 8-Port DVI Dual-Link (USB) SeriousBit NetBalancer The ServSwitch Wizard™ 8-Port DVI Dual- of the devices to all computers. The switch’s Link (USB) (KV2008A) from Black Box is the architecture combines transparent USB 2.0 How do you combine required network activi- to priorities, giving NetBalancer an advantage first product to feature USB True Emulation. protocol with emulated keyboard and mouse ties without getting slowed by bandwidth- over other similar tools. This breakthrough technology ensures that control. There are two dedicated keyboard/ hogging activities? Most traffic-shaping tools the full characteristics of the connected USB mouse USB ports on the switch’s console set speed limits for applications and processes, NetBalancer lets you: peripherals are passed to every system, so plus two USB 2.0 transparent ports for any though it is not very convenient. For example, (cid:127) Set download and upload network priority specialized features are quickly recognized USB 2.0 peripherals. you limit your downloading speed and surf your for any process. Current priorities include on the attached devices. What’s more, each favorite Web site. When you are done with surf- High, Normal, Low, Block Traffic, Ignore computer retains this information—even if the The user can share high-end video and any ing, the bandwidth is free, yet your downloading Traffic, and Limit Traffic device is plugged into another computer. four USB peripherals (including the keyboard speed is still limited. Dealing with limits implies (cid:127) Set download and upload speed limits and mouse) between up to eight workstations. constant tuning of your traffic-shaping program. (cid:127) Show all system processes with their in The switch lets users connect to up to four The switch offers true DDC EDID support. and out network traffic speed USB peripherals. Thanks to its USB True Switching can occur via hotkeys, mouse, With SeriousBit NetBalancer, such problems (cid:127) Show current connections for any process Emulation technology, the switch supports dry contacts, or even RS-232/V.24. The are obsolete. In addition to traffic limits, you can (cid:127) Show downloaded and uploaded traffic for HIDs (human interface devices) while still ServSwitch Wizard 8-Port DVI Dual-Link set download and upload priorities for all appli- any process since NetBalancer’s start working with traditional USB. It avoids many of (USB) is ideal for users who depend on high- cations. Applications with higher priority get (cid:127) View overall system traffic as a graph the limitations found in traditional emulations, resolution video performance and need the more bandwidth than those with lower priority. (cid:127) Show last 15 seconds of traffic enabling instantaneous switching and hotkey flexibility to use multiple peripheral devices. (cid:127) Fine-tune priorities with Level Severity support. Unlike other traffic-shaping software, NetBal- ancer does not limit low-priority applications SeriousBit When a user connects USB devices, the when high-priority ones don’t use the network. switch simultaneously emulates the character The limits are changed automatically according Performance and Reliability NETWORKING & VPN NETWORKING & VPN ConSentry Network’s ConSentry InSight Command Center now offers a real-time alert and corre- lation engine to help IT workers Force 10 Networks identify nonbusiness applications Virtualization Framework and devices on an enterprise’s utilizes a suite of ad- LAN posing security risks. vanced terabit-enabled Free to existing customers with cur- network virtualization rent support contract; LANShield software to make Switch pricing starts at $4,995 virtualized environments (408) 956-2100 easier to manage. www.consentry.com (866) 600-5100 www.force10networks.com Correlation Engine Identifies LAN Risks ConSentry Networks Manage Virtualized Environments With Ease ConSentry InSight Command Center Force10 Networks Virtualization Framework ConSentry Networks realizes that current finan- devices that are unmanaged. The software also Performance requirements are always chang- VirtualControl and VirtualScale help data cen- cial restraints are forcing enterprises to juggle features automatic remediation abilities. The ing, so data center managers need to have ters eradicate the need for spanning tree proto- keeping intellectual property safe while simulta- end result is considerably better end point pro- both visibility into the network’s performance cols, develop network durability, and segment neously operating under tightening budgets. To tection and operational savings. and the tools to ensure the data center is run- traffic for specific applications to boost man- that end, the ConSentry InSight Command ning in the most cost-effective way. Force10 ageability, while reducing troubleshooting diffi- Center software running within the company’s The core of the engine is a rules database that Networks delivers those capabilities through culties at both Layer 2 and Layer 3 NAC switches and controllers now includes a oversees and compares a range of inputs to its new Virtualization Framework. environments. VirtualView utilizes sFlow, a real-time alert and correlation engine that pin- sniff out risks to data and LAN availability. A set standards-based data collection protocol, to points nonbusiness usage of LAN-based of included predefined rules automatically high- Force10 Networks’ Virtualization Framework give users both real-time traffic monitoring and devices and applications posing a potential risk lights the most common risks currently to LANs suite combines three terabit-enabled network the ability to orchestrate resources through to an enterprise’s data. Further, new dash- and reports the findings via dashboard alerts management programs—VirtualControl, Virtu- policies using open software and technologies. boards, including NAC and Questionable and reports. Its ability to drill down to Layer 7 alScale, and VirtualView—to let data center These technologies include an industry-stan- Activity versions, provide IT staff with visual activity as part of the stateful flow analysis pro- managers build, design, troubleshoot, and dard CLI (command-line interface) and SNMP. details that identify the specific users, devices, vides IT staff with the information needed to benchmark network and application perform- In the future, XML-based commands and con- and applications posing that risk. take immediate action and for longer-term items ance in virtualized environments. With the trol provisioning middleware will also be in- such as LAN usage blueprints, audits, and software components of the Virtualization cluded. The Virtualization Framework is part of Also aiding in protection is new end-point pos- forensics. Framework suite, users can partition physical Force10 Networks’ operating system, FTOS. ture validation software that’s integrated into network assets to virtualize logical bound- ConSentry’s LANShield platform software. The aries, consolidate physical network fabrics to software includes a permanent agent for man- virtualize physical boundaries, and inspect aged devices and a dissolvable agent for guest and automate network behavior.