CertsChief Guaranteed Success with Accurate & Updated Questions. Scrum SSM SAFe 5 Scrum Master (SSM) Questions & Answers PDF For More Information - Visit: https://www.certschief.com/ ProductFull Version Features: 90 Days Free Updates 30 Days Money Back Guarantee Instant Download Once Purchased 24/7 Online Chat Support Visit us athttps://www.certschief.com/ssm/ Latest Version: 7.0 Question: 1 When is iteration planning completed? A. When iteration goals are defined B. When the team commits to the plan C. When story analysis is complete D. When the team capacity is determined Answer: B Question: 2 When estimating stories, what is the Scrum Master's key responsibility? A. Ensure everyone on the team participates B. Provide information about customer needs C. Ensure the team gives accurate estimates D. Limit discussion to manage timeboxes Answer: A Question: 3 What is a characteristic of an effective Scrum Master? A. Understands customer needs B. Is a technical expert C. Gives open, honest opinions D. Removes all conflict Answer: D Question: 4 Which team dysfunction does SAFe help address with the help of Business Owners? Visit us athttps://www.certschief.com/ssm/ A. Lack of visibility B. Avoidance of accountability C. Missed timeboxes D. Lack of transparency Answer: B Question: 5 What foundational issue most often leads to team dysfunction? A. Weak Lean-Agile leadership B. Fear of conflict C. Lack of commitment D. Absence of trust Answer: D Question: 6 Why is it important for the Scrum Master to help the team focus on daily and Iteration goals? A. To keep the Team Backlog to a manageable size B. To facilitate the team's progress towards the current PI Objectives C. To help the team maintain their velocity D. To eliminate impediments Answer: B Question: 7 What is one benefit of program increment (PI) objectives? A. They describe a process for defining team goals B. They form a guiding coalition C. They ensure accurate status reporting D. They create a near-term focus and vision Answer: D Visit us athttps://www.certschief.com/ssm/ Question: 8 What is the goal of the scrum of scrums event? A. To review the Agile Release Train's progress toward its PI Objectives B. To review each team's progress on its Stories C. To focus on Agile Release Train process improvement D. To demo Features to Product Management Answer: A Question: 9 Which two practices are recommended in SAFe for root cause analysis? (Choose two.) A. Post-PI Planning meeting B. Fishbone diagram C. Weighted shortest job first D. 5 Whys E. Iteration retrospective Answer: B,D Question: 10 What are two outputs of Iteration Planning? (Choose two.) A. PI Objectives B. Iteration backlog C. Iteration goals D. Program Backlog E. Team Backlog Answer: B,C Visit us athttps://www.certschief.com/ssm/ For More Information - Visit: http://www.certschief.com/ Discount Coupon Code: Page | 1 CE RTSCHhtItpE:/F/w1w0w .cVeisrit tuss cathhtitpesf:/./wcwowm.ce/rtescxhaiefm.co/m0/sBsm0/-104/ Powered by TCPDF (www.tcpdf.org)