DR. SANJAY V. PATIL HEAD AND TECHNICAL ADVISER DEPARTMENT OF ALCOHOL TECHNOLOGY VASANTDADA SUGAR INSTITUTE, MANJARI, PUNE (INDIA) Email: [email protected] AIDA Technical Seminar www.vsisugar.com Bengaluru, 05-06-Oct-2017 Types of assessments Norms – SW Treatment/Disposal Approved ZLD systems Approach Fermentation and Distillation Effluent quantities and Characteristics Biomethanation Reverse osmosis Multiple effect Evaporation Biocomposting Slop fired Incineration boiler BMSW dryer Condensate Polishing unit On-line monitoring system and other requirements Conclusions AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e Self Assessment Third Party Assessment- VSI/NEERI/Distillers’ Association etc Assessment by regulatory authority- SPCB/CPCB/MoEF AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e 1. Red category and Zero Liquid Discharge (ZLD). 2. For Bio-composting as a final treatment: MEE is essential SW storage max. 30 days on raw SW basis. Max. 270 days (With covered compost yard- additional/throught-out the year can be allowed) Yard has to be impervious as per CREP norms. Bio-compost has to be bagged in polybags & compost composition & manufacturers name to be printed on it. Compost quality has to be certified by Ministry of Agriculture. AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e 2. For Bio-composting as a final treatment (Continued): For 5 to 12 % solids containing spent wash, the filler material (PMC) to spent wash ratio prescribed is 1: 2.5 for 45 days cycle and 1:3.5 for 60 days cycle. For concentrated spent wash (20 to 30 % solids), the filler material (PMC) to spent wash ratio prescribed is 1: 1.6 for 60 days cycle. Impervious compost yard area based on material balance (plus ready compost storage area) should be made available. During rainy season, bio-composting process has to be stopped. Record of filler material used (PMC) and bio- compost produced/sold should be maintained. AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e 3. SW storage- Impervious as per CREP norms. 4. For Incineration route: Storage of 7 days on conc. SW basis in impervious storage tank. 5. Secondary treatment: Process condensate, permeate, spent lees, CT & boiler Blowdown, pump gland cooling water etc. has to be treated (CPU) & recycled back. 6. Online monitoring : Mass flowmeters before & after concentration of SW. Camera: 30 days SW storage tank & bio-compost yard. Stack Monitoring System (PM <150 mg/NM3 or 50 mg/NM3). To be installed & connected to SPCB/CPCB server. AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e 1 Biomethanation MEE Bio-composting 2 Biomethanation RO MEE Bio-composting 3 Biomethanation MEE DRYER 4 Biomethanation RO MEE DRYER 5 MEE Incineration AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e 1. Holistic Approach: Integrated management employing Reduce-Recycle-Reuse principle 2. No End of Pipe Treatment. 3. No Discharge 4. Analytical & Necessary measurement facilities (Water, Steam, Power, Effluents) 5. Fresh water consumption-section wise 6. Environment Management Cell: (Unit Head + Distillery Manager + ET plant I/c + Concerned Officers/Chemists) AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e Distillery installed and Licensed capacity. Boiler capacity. Source of electricity and water. Distance from river/dam/canal/other water bodies. Authentic data on alcohol production/molasses consumed. Per day alcohol production data. Authentic data on per day SW & SL production, total SW & SL production. No. of days of operation in a year. Alcohol % (v/v) achieved in wash, Fermentations efficiency, Distillation efficiency, Recovery etc. Fermentation technology employed. Distillation technology employed, reboilers used, spent lees generation (Rectifier, PRC etc). If sludge is generated, quantity of sludge MT/day & its method of disposal. AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e RAW VALUES SPENT LEES VALUES SPENT WASH Total SL, M3/Day Volume, M3/Day Volume, L/L Volume, L/L SL Recycled, M3/Day pH SL for treatment COD, mg/L M3/Day BOD, mg/L pH TDS, mg/L COD, mg/L BOD, mg/L TSS, mg/L TDS, mg/L Volatile acids, TSS, mg/L mg/L AAAIDIIDDAAA 2 TT0ee1cc7hhnniiccaall SSeemmiinnaarr O c t o b e r 0 5 - 0 6 , 2 0 1 7 w w w . v s i s u g a r . c o m V a s a n Btdeandgaa lSuurugw,a w0r w5In.-v0sst6iits-uOutcgeta,- 2rP.0cuo1nm7e
Description: