ebook img

ANCILLARY ARBITRATION ISSUES IN CONSTRUCTION DISPUTES Lionel M. Schooler1 ... PDF

28 Pages·2008·0.23 MB·English
by  
Save to my drive
Quick download
Download
Most books are stored in the elastic cloud where traffic is expensive. For this reason, we have a limit on daily download.

Preview ANCILLARY ARBITRATION ISSUES IN CONSTRUCTION DISPUTES Lionel M. Schooler1 ...

ANCILLARY ARBITRATION ISSUES IN CONSTRUCTION DISPUTES Lionel M. Schooler1 INTRODUCTION The use of arbitration as a means of alternative dispute resolution is well-known in the construction industry. What is less well-understood is the breadth and impact of the arbitration process, particularly who can be compelled to participate in an arbitration proceedingand the impact ofsuch an award on subsequent disputes.This Article explores the interstices of this process through the mechanics of an elaborate hypothetical (but all too realistic) scenario about the construction of the Spindletop Office Building. THE BUILDING OF THE SPINDLETOP OFFICE BUILDING: INCEPTION OF THE PROJECT In January of 2000, Oliver Owner, a well-known Texas oilman, decided to build a new office complex in Houston, Texas,named “Spindletop.”He contracted withAlex Architect to design plans and specifications for Spindletop. The contract for architectural services between Oliver and Alex contained,among other things, an arbitration clause invoking the Federal Arbitration Act, and also provided that any other arbitration proceeding instituted by Owner could not require consolidation of Owner’s claims against Alex without Alex’s written consent. The contract also called for fifty percentofAlex’s payment to be withheld for one year, at which time the Project was scheduled to be substantially complete. After working day and night for three weeks, Alex completed the designs and specifications and took them to Oliver Owner for review.Mr. Owner was so excited about the plans for his new building that he barely glanced at them before inviting bids for the construction of Spindletop from twenty localgeneral contractors with whom he had worked on other projects. 1Lionel M. Schooler is a partner in the law firm of Jackson Walker L.L.P. and a member of the panel of arbitrators of the American Arbitration Association. 3958143v.1 One such general contractor was Greg Cummings, Incorporated(“GCI”).Greg Cummings was very excited to have the opportunity to bid on Spindletop.In preparinghis general contractor’s bid, Mr. Cummings obtained bids from numerous subcontractors including Ernie’s Electrical and Hank’s Heating, Ventilating & Air Conditioning (“HVAC”). Ernie’s Electrical provided Greg Cummings with a bid for the electrical scope of work. To do so, Ernie’s Electrical solicited numerous bids for supplies, including one from Cam the Conduit Supplier.Ernie’s Electricalrelied upon Cam’s bid when submitting the electrical bid.Hank’s HVACalso solicited numerous bids for supplies. He received one from Derek the Duct Supplier for the HVAC supplies, upon which he relied when submitting his HVAC bid. Atthe bid opening in March, GCI was determined to be the low bidder on the Project with an acceptable bid, and Oliver Owner therefore signed a contract with GCI to construct Spindletop per Alex Architect’s plans and specifications.The contract between Oliver Owner and GCI contained a broad arbitration clause that stated “any and all controversies or claims arising out of and/or relating to the contract shall be resolved through binding arbitration pursuant to the Federal Arbitration Act.” After GCI signed the contract withOliver Owner, Greg Cummings contacted hissurety,Safe Bonding, to obtain Payment and Performance Bonds to comply with the requirements of the contract.Once he obtained the necessary bonds, Greg Cummings then signed contracts withthe low bidders upon whose numbers he had relied when formulating and submitting his bid. These low bidders included Ernie’s Electrical and Hank’s HVAC. GCI’s contract with Ernie’s Electrical contained an arbitration clause utilizing the same language as the contract between GCI and Oliver Owner. Hank’s HVAC also contained the same clause, but because Hankrefused to agree to anycontract with an arbitration clause, it was deleted from the contract that Hank’s HVAC and GCI signed. 2 3958143v.1 After receiving the signed contract with GCI, Ernie’s Electrical solicited an invoice from Cam the Conduit Supplier for the electrical supplies needed to perform the electrical scope of work. Cam’s invoice contained an arbitration provision. Upon hearing his companywas the low bidder, Hank immediately contracted with Derek the Duct Supplier for the duct and other HVAC supplies needed to complete that scope of work.This contract did not have anarbitration clause. THE BUILDING OF THE SPINDLETOP OFFICE BUILDING: EVENTS AT THE JOB SITE The construction of the Project commenced.Within four months, the foundation and shell of the building were complete.However, a few weeks later, the weather turned cold and wet.While the shell of the building was intact, the windows and doors were not installed and rain water managed to infiltrate the building. Knowing that the completion date was quickly approaching, GCI’s job superintendent and job foreman ordered work to continue despite the presence of standing water throughout the building. Outside in the mud, Ernie’s Electrical crew diligently tried to locate the electrical main shown on the plans to tie into it and supply the building with electricity. After numerous failed attempts, Ernie’s contacted the local utility company for assistance in locating the electrical main and was informed that the actual location was more than three hundred yards away from the designated location. Ernie’s Electrical promptly notified GCI ofthe discrepancy and submitted a change order for the additional material and labor itestimated would be required to trench the extra three hundred yards to install the underground electrical connections. In consultation with Alex the Architect, GCI rejected the change order, stating that the contract with Ernie’s Electricalcalled for Ernie’s Electrical to locate and make connections to the electrical main as needed.GCI thusinsisted that the additional three hundred yards oftrenching was part ofErnie’s Electrical’s scope of work and refused to agree to payanyadditionalmoney for this 3 3958143v.1 work. The parties spent several days in fruitless discussions, and ultimately, when the stalemate could not be resolved, Ernie’s Electrical’s crew walked off the Project site. Hank’s HVAC continued working diligently inside the building installing the HVAC components of the project.After installing the duct, thermostats, compressors, air handlers, and other necessary accessories, Hank’s HVACcontacted GCI to inform it that electrical power was needed to provide energyto the HVAC units. After Ernie’s Electrical walked off the job, GCI was not able to locate a replacement electrical subcontractor. GCI therefore called Ernie back and told Ernie it would sign Ernie’s Electrical’s proposed change order if Ernie would return to the Project immediately and install the underground electrical supply required to provide power to the building. By the time Ernie’s Electrical returned to the job site, nearly six weeks had elapsed. Ernie’s Electrical proceeded to install the underground electrical connections but the six-week delay in completing this task prevented the use of the HVAC equipment at the job site for eight weeks. In this two month interim, the interior subcontractors had continued to work at the instruction of GCI’s project superintendent. The drywall, insulation, and ceiling tiles were installed and the millwork neared completion. When the HVAC system was finally turned on, however, GCI discovered that the delay had caused mold to develop on the drywall, insulation, and ceiling tiles. Responding to this development, GCI retained the services of a mold consulting firm to conduct tests in the building.Its report identified the HVAC system as being entirely inadequate to provide positive pressure in the buildingand attributedthe presence of mold to a negative pressure condition existing inside the building which drew outside water into the building, causing the mold. GCI notified Hank’s HVAC of the test results and suspended payment of any progress payment application submitted by or pending from Hank’s HVAC. In response, Hank’s HVAC 4 3958143v.1 issued a notice of default to GCI and a claim of lien for unpaid work, but this notice was not sent within the twenty-one days required by the terms and conditions of the contract between GCI and Hank’s HVAC. When Oliver Owner learned of this, he insisted that GCI replace all the interior finishes and complete the project according to the original schedule. Relying upon the mold report, GCI insisted Oliver Owner sign a time and materials change order before agreeing to proceed with mold remediation. Oliver Owner rejected this request and suspended payments to GCI. He also notified Alex the Architect of a potential breach by Alex regarding this disputeand invoked the penalty clause of the contractbetween Owner and Architect to suspend the deadline for paying the balance of Architect’s fee. Oliver Owner then contacted Safe Bonding, insisting that it complete the project under its Performance Bond.Safe Bonding replied that the terms of the bond were not satisfied and refused to complete the project. THE BUILDING OF THE SPINDLETOP OFFICE BUILDING: THE DISPUTES A. Lawsuits Are Filed Wearyofthe mounting problemsand threats of lien,which created concerns over potential defaults with his financing, Oliver Owner filed suit against GCI and Safe Bonding for breach of contract and violations of the Texas Deceptive Trade Practices Act (“DTPA”).2Oliver Owner also sued Alex Architect, Hank’s HVAC, and Ernie’s Electrical for negligence for designing and installing inadequate HVAC equipment. After learning of the suit, GCI immediatelyfiled a counterclaim against Oliver Owner for breach of contract and asserted a lien claim against the Project. GCI also stopped paying its subcontractors because itwas not being paid by Oliver Owner.As a result, the subcontractors were 2TEX.BUS.&COM.CODE§§ 17.45 et seq. 5 3958143v.1 unable to pay their suppliers. GCI also filed suit against Alex Architect for negligent design in providing plans and specifications with an inadequate HVAC design. Alex Architect filed suit against Oliver Owner for breach of contract for not paying the outstanding balance of fiftypercent of his fee. After not receiving payment, Ernie’s Electrical filed suit against GCI for quantummeruit for failure to payfor the change order work to install the underground electrical from its new location. On being notified of the lawsuit by Ernie’s Electrical, GCI filed a counterclaim for breach of contract for Ernie’s abandonment of the job.Camthe Conduit Supplier, who had not been paid by Ernie’s Electrical, filed a lien against Spindletop and filed a suitagainst Ernie’s Electrical for breach ofcontract.Hank’s HVAC stoppedpaying Derek the Duct Supplier because Hank’s HVAC was not paid by GCI.Hank’s HVACalso filed a lawsuit against GCI for breach of contract as well as a lien against Spindletop.Derek filed a lien against Spindletop and filed a breach of contract claim against Hank’s HVAC. B. The Pending Claims As the result of the filing of all of these lawsuits, the following claims were outstanding when the dust settled. No. Plaintiff Defendant Claim Basis Failure to Perform; General Contractor Breach of contract; 1. Owner Failure to honor the and Bonding Co. DTPA bond Installing inadequate 2. Owner Architect Negligence HVAC HVAC Installing inadequate 3. Owner Negligence Subcontractor HVAC Electrical Installing inadequate 4. Owner Negligence Subcontractor HVAC Failing to payprogress General Counterclaim for 5. Owner payments and failing to Contractor breach of contract approve change order 6. General Architect Negligent Design Inadequate HVAC 6 3958143v.1 No. Plaintiff Defendant Claim Basis Contractor design Failing to pay50% of 7. Architect Owner Breach of contract fee Electrical General contractor Failing to payfor 8. QuantumMeruit Subcontractor and Owner change order work General Electrical Counterclaim for 9. Abandoning the job Contractor Subcontractor breach of contract Electrical Failure to payfor 10. Conduit Supplier Breach of contract Subcontractor supplies Owner/General Failure to payfor 11. Conduit Supplier Lien claim Contractor supplies HVAC General Contractor Breach of contract Failure to payfor work 12. Subcontractor and Owner and lien claim performed Owner/General Failure to payfor 13. Duct Supplier Lien claim Contractor supplies HVAC Failure to payfor 14. Duct Supplier Breach of contract Subcontractor supplies C. The Fora for Resolving the Disputes All of the lawsuits were consolidated into one proceeding in Harris County, Texas, state district court, the county where the Project was being constructed. As the court was assessing the multitude of claims, it noticed that several of the agreements attached to the pleadings contained arbitration claims and several of the responsive pleadings asserted pleas in abatement to require submissionofclaims to arbitrate.Thus, to assess the impact of arbitration as an alternative means of resolving disputes in the Spindletop litigation, the court realized that its first procedural step would be to determine whose claims were arbitrable, how they would proceed to arbitrate, and which parties could be compelled to arbitrate. ARBITRATION #1(DISPUTES AMONG THE OWNER,THE GENERAL CONTRACTOR,THE ELECTRICAL SUBCONTRACTOR AND ITS SUPPLIER) 7 3958143v.1 In light of the numerous claims against it, GCImoved the court to compel arbitration as to all the parties and all claims pursuant to the arbitration clause contained in the contracts it had with Oliver Owner and Ernie’s Electrical. The court noted that the claims in issue involved transactions in commerce as that termis used in the Federal Arbitration Act (“FAA”)3 and that the contract containing arbitration clauses also referred to adjudication of these clauses under the FAA. The court granted GCI’s motion to compel in part, citing In re Oakwood Mobile Homes, Inc.,4 holding that where there is a valid agreement to arbitrate and the subject dispute falls within the scope of that agreement, then signatories to that agreement are compelled to arbitrate.Therefore, Oliver Owner was directed by the court to arbitrate his breach of contract and DTPA claims against GCIbased upon the common nucleus of operative facts giving rise to these claims and the operative agreement to arbitrate in the contract between Oliver Owner and GCI.5 Ernie’s Electrical resisted compulsion to arbitrate its claims against GCI. Ernie’s acknowledged that it was a signatoryto a contract containing an arbitration agreement but argued that its claim was not subject to arbitration as being beyond the scope of the arbitration clause because it was suing in quantum meruit, not breach of that contract. The court overruled this objection and held that Ernie’sElectrical’s change order claim was subject to arbitration on the basis of Dustrol, Inc. v. Champagne-Webber, Inc.,6which upholds the arbitration of change order claims based upon a broadly wordedarbitration agreement in the original contract.The court found that, regardless of the nature of the relief claimed by Ernie’s Electrical, the relationship it had with GCI 39 U.S.C. § 2(2000). 4987 S.W.2d 571 (Tex. 1999)(orig. proceeding). 5Jack B. Anglin Co., Inc. v. Tipps, 842 S.W.2d 266, 271 (Tex. 1992). 6Dustrol, Inc. v. Champagne-Webber, Inc., No. CIV.A.3:01-CV-0650-G, 2001 WL 1326477 (N.D. Tex. Oct. 16, 2001). 8 3958143v.1 arose from an agreement containing an arbitration clause by which Ernie’s Electrical was bound. The court also held that all of Ernie’s Electrical’s counterclaims against GCI would be arbitrated in the same proceeding, except for the issue of enforcement of Ernie’s Electrical’s claim of lien. In response to the court’s holding, Ernie’s Electrical sought to compel Oliver Owner to arbitrate its negligence claimagainst Ernie’s Electrical.Relying upon Associated Glass, Ltd. v. Eye Ten Oaks Investments, Ltd.,7 the court granted Ernie’s Electrical’s motion to compel. Therefore, Oliver Owner, a non-signatory to such a contract, was directed to arbitrate his negligence claim against Ernie’s Electrical in the same arbitration proceeding as the one adjudicating the disputes between GCI and Ernie’s Electrical. Ernie’s Electricalalso requested the court compel Cam the Conduit Supplier to arbitrate its claim against Ernie for breach of contract on the basis of the arbitration clause in the invoice issued by Cam’s to Ernie’s Electrical, including Cam’s lien claims. Cam objected to arbitrating his lien claims, contending that such claimswere not subject to any contract and were statutorily based.On the basis of the holding in Dalton Contractors, Inc. v. Bryan AutumnWoods, Ltd.,8the court granted Ernie’s Electrical’s motion and required Cam’s lien claims to be arbitratedin the same proceeding.9 ARBITRATION #2(DISPUTES AMONG THE OWNER,THE GENERAL CONTRACTOR,AND THE HVACSUBCONTRACTOR) 7Associated Glass, Ltd. v. Eye Ten Oaks Invs., Ltd., 147 S.W.3d 507 (Tex.App.—San Antonio 2004, no pet.)(building owner's claims against glass installation subcontractor and masonry subcontractor for negligence, fraud, fraudulent concealment, and negligent misrepresentation, relating to water incursions and moisture accumulationarose out of or were related to subcontractors' contractual duties under their subcontractswith general contractor, and thus, owner was bound by arbitration provision of subcontract, though owner was not a party to subcontracts). 8Dalton Contractors, Inc. v. Bryan AutumnWoods, Ltd., 60 S.W.3d 351 (Tex.App.—Houston [1st Dist.] 2001, no pet.). 9SeeCVN Group, Inc. v. Delgado, 95 S.W.3d 234 (Tex. 2002) (scope of agreement to arbitrate can control arbitrability of mechanics’ lien claims). 9 3958143v.1 GCI sought to have claims asserted by Hanks’ HVAC against it dismissedon the basis that Hanks’ HVAC had failed to timely submit claims within the terms oftheir applicable agreement. Alternatively, GCI sought to compel to arbitration the claims asserted by Hank’s HVAC. Hank’s HVAC resisted being compelled to arbitrate on the basis that it did not have any written agreement to arbitrate with GCI, nor one that was enforceable by GCI. The court first considered the question of arbitrability of Hank’s HVAC’s claim under quantum meruit, which required it to examine the jurisprudence of compelling non-signatories to arbitrate, including the recent, far-reaching decision of the Texas Supreme Court in In Re Kellogg Brown &Root.10 THE IMPACT OF IN RE KELLOGG BROWN &ROOT The court analyzed the historyofthe jurisprudence of compelling non-signatories to arbitrate. The court noted that several earlier cases had evaluated this issue,11withthe majorityholding that in certain instances, non-signatories could be compelled to arbitrate. The court then focused upon recent decisions by the Texas Supreme Court.In the first, In Re FirstMerit Bank,12the court noted that the supreme court upheld arbitrability against non-signatories who were attempting to invoke the benefits of a contract thatcontained an arbitration agreement.In the second, In Re Halliburton,13the court noted that the supreme court upheld arbitrabilityagainst non-signatories in an employment context, where the non-signatories by their conduct (e.g., 10No. 03-1129, 2005 WL 1187775 (Tex. May 20, 2005). 11CompareNationwide of Bryan v. Dyer, 969 S.W.2d 518 (Tex.App.—Austin 1998, no pet.)(upholding arbitrabilityas to non-signatories); In Re Rangel, 45 S.W.3d 783 (Tex.App.—Waco 2001, no pet.)(same); In Re James Keith Rose, 82 S.W.3d 523 (Tex.App.—Corpus Christi 2002, no pet.) (same);withIn Re Conseco Fin., 19 S.W.3d 562 (Tex.App.— Waco 2000, no pet.)(preventing arbitrability as to non-signatories); Southwest Tex.Pathologyv. Roosth, 27 S.W.3d 204 (Tex.App.—San Antonio 2000, no pet.)(same); Fleetwood Enters.v. Gaskamp, 280 F.3d 1069 (5thCir. 2002)(same). 1252 S.W.3d 749 (Tex. 2001). 1380 S.W.3d 566 (Tex. 2002). 10 3958143v.1

Description:
Spindletop from twenty local general contractors with whom he had worked on other projects. This contract did not have an arbitration clause.
See more

The list of books you might like

Most books are stored in the elastic cloud where traffic is expensive. For this reason, we have a limit on daily download.